ELE02-02558
| Electrical Rough-In | 10/3/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | A | PART |
|
|
ceiling ; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
ELE02-02758
| Electrical Rough-In | 10/3/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 10/03/2002 at 11:36:27. Contact: ###-####.
Hard ceilings ok 10/4/2002 9:06:21 AM
|
ELE00-01776
| Electrical Rough-In | 10/3/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | A | NR |
|
|
###-####--JON
Had conf box fill and #14 on 20 amp ckt 10/4/2002 12:16:55 PM
|
ELE02-02662
| Final | 10/3/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | A | PASS |
|
|
We were not the contractor that did the work in the closet. Inspector doesnt't need to go back to this site per conversation with pat on 10/3. Marv; Phone #: ###-#### Internet Inspection Request from: Dan Mitchell
|
ELE02-03054
| Temporary Service | 10/4/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | P | FAIL |
|
|
###-#### vivian
no ground 10/4/2002 1:32:38 PM
|
ELE02-00568
| Final | 10/4/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
ELE02-01914
| Final | 10/4/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | P | PASS |
|
|
ALAN ###-#### LIGHTING IN POOL
|
ELE02-03066
| Rough-In Permanent Service | 10/3/2002 | 10/4/2002 | 10/4/2002 12:00:00 AM | P | PASS |
|
|
###-#### ALLEN
P/S U/G N Ok 10/4/2002 1:03:09 PM
|