ELE18-03669
| Final | 10/3/2018 | 10/4/2018 | 10/4/2018 2:01:16 PM | P | PASS |
|
|
Final Inspection any questions please call Louis at ###-#### Phone #: ###-#### Inspection requested via web by Louis Keller Ok final. Ground bar installed for grounds at bottom of panel. Ground rod driven, and jumper installed.
|
ELE18-03800
| Permanent Service | 10/3/2018 | 10/4/2018 | 10/4/2018 1:44:42 PM | A | CANC |
|
|
existing light pole on South corner of intersection. install mast and wire to disconnect and owner provided and mounted equipment. Please call Paul at ###-#### Phone #: ###-#### Inspection requested via web by Steve Blackmer Re-scheduled for 10/5/18. Talked to electrician to find out exact location. Was not in area. Will inspect 10/5/18 in the AM.
|
ELE18-02754
| Final | 10/3/2018 | 10/4/2018 | 10/4/2018 1:42:05 PM | P | PART |
|
|
Partial final Phone #: ###-#### Inspection requested via web by cris flores Partial final. Ok to stock and install shelves. Employees only for training and other related purposes. Not open to outside public. Check for KO seal top of stairs in storage area. 1 outside light on NE corner of building needs installed. Electrical in kiosk areas and pharmacy awaiting manufacturer ends for power hookup. Back wall in pharmacy area has sink with large partition seperating itself from 2 lower recepts that are going to be used for computer related work. Was not going to require GFI protection.
|
ELE18-03759
| Final | 10/3/2018 | 10/4/2018 | 10/4/2018 12:59:24 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Eric Schroeder Ok final. This is to close out permit. Panel labeled and intersystem installed.
|
ELE18-02554
| Electrical Rough-In | 10/2/2018 | 10/4/2018 | 10/4/2018 12:46:36 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Katie Sitterle Ok cover kitchen. Existing #12 feeding dining is now abandoned. Wires are disconnected and left in the wall.
|
ELE17-03951
| Electrical Rough-In | 10/4/2018 | 10/4/2018 | 10/4/2018 11:08:50 AM | A | PASS |
|
|
Contact: Clayton Pennington...wall rough-in 6 classrooms, 2nd floor please Phone #: ###-#### Inspection requested via web by Deb Gooden Ok cover 5 classrooms 2nd floor.
|
ELE16-02728
| Final | 10/4/2018 | 10/4/2018 | 10/4/2018 11:07:26 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Louis Keller Ok final. Service overhead moved out of pool path as per code. Service already energized.
|
ELE18-03257
| Electrical Rough-In | 10/3/2018 | 10/4/2018 | 10/4/2018 10:28:36 AM | A | PASS |
|
|
Installed PVC for hot tub and water feature power. Most of the backyard will be all done in concrete. you can walk through the garage to go around back any questions please let me know. Phone #: ###-#### Inspection requested via web by David Kubik Ok cover conduit for water feature and hottub.
|
ELE17-00480
| Electrical Rough-In | 10/3/2018 | 10/4/2018 | 10/4/2018 9:41:19 AM | A | PASS |
|
|
Rough in Garage Phone #: ###-#### Inspection requested via web by Don Conley Ok cover. Corrections made.
|
ELE18-03785
| Rough-In Permanent Service | 10/3/2018 | 10/4/2018 | 10/4/2018 9:21:39 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk p/s u/g n ok
|
ELE18-03801
| Permanent Service | 10/3/2018 | 10/4/2018 | 10/4/2018 9:21:00 AM | A | PASS |
|
|
existing light pole on South corner of intersection. install mast and wire to disconnect and owner provided and mounted equipment. Please call Paul at ###-#### Phone #: ###-#### Inspection requested via web by Steve Blackmer Received pics of disc and weatherhead on pole. p/s o/h n ok AFC needed for final.
|
ELE18-03796
| Rough-In Permanent Service | 10/3/2018 | 10/4/2018 | 10/4/2018 9:20:20 AM | A | PASS |
|
|
THE PEDESTAL IS ABOUT A BLOCK PAST THE VAULT AT 61 W. HORIZON DR. PLEASE CALL BEFORE GOING. Phone #: ###-#### Inspection requested via web by Lori Stout p/s u/g n ok AFC needed for final.
|
ELE18-03270
| Permanent Service | 10/3/2018 | 10/4/2018 | 10/3/2018 2:45:18 PM | A | PASS |
|
|
Pat Phone #: ###-#### p/s o/h rec ok. Homeowner to contact IDP before energize.
|
ELE18-03461
| Final | 10/3/2018 | 10/4/2018 | 10/3/2018 1:15:42 PM | A | PASS |
|
|
Talked to contractor. Fees were updated according to work done. Fees are correct. Ok final.
|