FIR11-00250
| INSP-Final Inspection | 9/28/2011 | 10/5/2011 | 10/5/2011 5:31:18 PM | P | PASS |
|
|
Scope of work passed inspection. Permit finaled.
|
BLD11-02072
| FIRE-Final Inspection | 10/5/2011 | 10/5/2011 | 10/5/2011 5:29:35 PM | P | NR |
|
|
|
BLD11-02291
| FIRE-Conference | 10/5/2011 | 10/5/2011 | 10/5/2011 5:28:54 PM | P | DONE |
|
|
On site conference regarding remodel work and the existing fire sprinkler system coverage related.
|
FIR11-00186
| INSP-Final Inspection | 10/5/2011 | 10/5/2011 | 10/5/2011 5:24:10 PM | P | PASS |
|
|
Fire alarm permit finaled.
|
FIR11-00355
| INSP-Sprinkler Rough-in | 10/4/2011 | 10/5/2011 | 10/5/2011 5:23:14 PM | A | FAIL |
|
|
Hydrostatic test of the overhead system failed due to a 10 psi. pressure loss at the guage. Relocated heads at the 1st floor corridor and 2nd floor utility rooms okayed.
|
FIR11-00505
| INSP-Final Inspection | 10/4/2011 | 10/5/2011 | 10/5/2011 12:40:10 PM | A | PASS |
|
|
Fire sprinkler permit final approved. Scope of work is finished.
|
FIR11-00505
| INSP-Sprinkler Rough-in | 10/5/2011 | 10/5/2011 | 10/5/2011 12:38:46 PM | A | PART |
|
|
Overhead fire sprinkler modification approved for cover.
|
FIR11-00186
| INSP-Alarm Testing | 10/4/2011 | 10/5/2011 | 10/5/2011 12:34:51 PM | A | PASS |
|
|
After hours reinspection passed, functional testing completed. C/N items and plan modifications verified.
|
BLD11-00783
| FIRE-Conference | 10/4/2011 | 10/5/2011 | 10/5/2011 12:29:58 PM | A | DONE |
|
|
On site conference regarding remodel schedule, related fire alarm and sprinkler trade permit work, life safety items.
|
FIR11-00414
| INSP-Sprinkler Rough-in | 10/4/2011 | 10/5/2011 | 10/5/2011 12:27:33 PM | A | PART |
|
|
UG fire supply line flush completed satisfactory.
|
BLD11-02236
| FIRE-Final Inspection | 10/4/2011 | 10/5/2011 | 10/5/2011 8:46:49 AM | A | PASS |
|
|
Life safety inspection passed.
|