FIR11-00095
| INSP-Final Inspection | 10/4/2011 | 10/5/2011 | 10/6/2011 8:44:37 AM | P | FAIL |
|
|
The forward flush passed. Can final this permit when the interconnections with the fire control panel have been verified. I was unable to verify interconnections due to fire alarm system issues.
|
FIR11-00382
| INSP-Alarm Testing | 10/4/2011 | 10/5/2011 | 10/6/2011 8:43:09 AM | P | FAIL |
|
|
No testing was done due to test reports and the NFPA 72 testing and inspection reports not being provided as per the review comments prior to an inspection. I did perform a walk through with the electrician and the fire alarm tech to verify audio visual spacing and candella settings. I found devices in several locations overspaced and additional devices needed in other areas. The fire alarm panel has also been relocated from the Electrical Room to the Server Room. A smoke and a heat detector have been added at the top of the elevator shaft. After a phone conversation with the fire alarm plan reviewer it was agreed that plan modifications are required prior to continuing an inspection. The main issue is the End of Line voltages have been calculated close to the acceptable limits. The device changes and panel relocation has the potential to have adverse effects on the calculations.
|
FIR07-00757
| FIR-Aging Inspection | 10/5/2011 | 10/5/2011 | 10/6/2011 8:42:13 AM | | NR |
|
|
I forwarded this permit number and status to scott for further action.
|
FIR05-00021
| FIR-Aging Inspection | 10/5/2011 | 10/5/2011 | 10/6/2011 8:41:14 AM | | NR |
|
|
I forwarded this permit number and status to scott for further action.
|
FIR11-00514
| INSP-Final Inspection | 10/4/2011 | 10/5/2011 | 10/5/2011 1:14:28 PM | A | FAIL |
|
|
Permit can be finaled when the correct transformer to the AES has been installed
|