Inspections for the day of: Friday, October 5, 2012.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR11-00195 FIR-Aging Inspection10/5/201210/5/201210/10/2012 9:31:51 AM NR
See conference notes
FIR11-00296 FIR-Aging Inspection10/5/201210/5/201210/8/2012 12:09:37 PM NR
Mark is working on this permit. An email has been sent to Scoot by Mark requiesting furhter action.
FIR12-00314 INSP-Sprinkler Rough-in/Hydro10/5/201210/5/201210/5/2012 4:07:38 PMPPASS
24 horu test passed.
BLD12-00550 FIRE-Final Inspection10/4/201210/5/201210/5/2012 3:55:34 PMPCANC
Overbooked. I contacted Peter and we agreed to reschedule for monday morning. I can find no record of a sprinkler permit for the changes that were needed per the previous conference. Peter stated the original contractor was no longer there and he did not know about sprinkler requirements.
FIR12-00198 INSP-Final Inspection10/5/201210/5/201210/5/2012 3:44:23 PMPPASS
Permit finaled
BLD12-00388 FIRE-Final Inspection10/5/201210/5/201210/5/2012 3:36:06 PMPPASS
Life safety passed per inspector 410
FIR12-00487 INSP-Sprinkler Rough-in/Hydro10/4/201210/5/201210/5/2012 3:20:29 PMAPASS
The overhead hydro test passed inspection.
FIR12-00393 INSP-Sprinkler Rough-in10/4/201210/5/201210/5/2012 3:15:47 PMAFAIL
Provide "job site copy" city approved plans for inspection, three upright heads on two lines (six total heads) are blocked by truss webbing, branchline restraint is missing, earthquake bracing is missing, wrong extended coverage pendants have been installed which will require a plan modification, as-builts will atleast be needed to show the pipe routing changes, one upright head at the mezzanine walkway appears to be overspaced. Ceiling tile can be installed since items needing correction can be viewed from the mechanical walkway.
BLD11-02317 FIRE-Final Inspection10/4/201210/5/201210/5/2012 1:37:56 PMACANC
I left voice message for Bruce stating that before I can perform a life safety inspection I would need the revised building plans. Per the online activities plans were resubmitted on 10/1/2012 and are still in the "review status" with a note from the plan reviewer stating that only the council chambers are approved. No inspection was performed.
FIR12-00343 INSP-Final Inspection10/4/201210/5/201210/5/2012 12:42:01 PMAPASS
Permit finaled.
FIR12-00456 INSP-Final Inspection10/4/201210/5/201210/5/2012 11:52:32 AMAPASS
Permit finaled. Netcon was a 5
FIR12-00091 INSP-Final Inspection9/25/201210/5/201210/5/2012 11:50:49 AMAPASS
permit finaled
FIR12-00087 INSP-Final Inspection9/25/201210/5/201210/5/2012 11:00:03 AMAFAIL
Monitoring station did not receive any of our test signals. Steve is going to inverstigate.
BLD12-02648 FIRE-Final Inspection10/4/201210/5/201210/5/2012 10:53:10 AMAFAIL
Remove the thumbturn deadbolt and provide keyed hardware with the sticker as discussed, provide single action hardware on the west exit door and remove the deadbolt, provide resubmittals showing the attic/mezzanine storage access including the stairs/ladder. See the city approved plans for corrections marked in red.
BLD12-02647 FIRE-Final Inspection10/4/201210/5/201210/5/2012 10:51:49 AMAFAIL
Remove the thumbturn deadbolt and provide keyed hardware with the sticker as discussed, provide single action hardware on the west exit door and remove the deadbolt, provide resubmittals showing the attic/mezzanine storage access including the stairs/ladder. See the city approved plans for corrections marked in red.
FIR12-00198 INSP-Final Inspection10/4/201210/5/201210/5/2012 10:00:12 AMAFAIL
Provide map at the facp with a legend so the responding fire dept. can interpret the map, provide as-built floor plan that is to scale (as the original submittal), provide NFPA 72 record of completion forms.
FIR12-00089 INSP-Final Inspection9/25/201210/5/201210/5/2012 8:07:10 AMAPASS
permit finaled
BLD12-00865 FIRE-Final Inspection10/4/201210/5/201210/5/2012 7:46:37 AMAPASS
Life safety passed. Revise floor plan is on site.