Inspections for the day of: Monday, October 5, 2015.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00501 INSP-Sprinkler Rough-in/Hydro10/5/201510/5/201510/5/2015 3:50:31 PMPPART
200 psi hydrostatic test passed/complete. 24 hour air test started at 3:30pm at 50 psi.
BLD15-03468 FIRE-Final Inspection10/2/201510/5/201510/5/2015 10:12:39 AMAPASS
Life fire safety passed/complete
BLD15-00623 FIRE-Final Inspection10/2/201510/5/201510/5/2015 9:30:41 AMAPASS
Life fire safety passed/complete
BLD15-03318 FIRE-Final Inspection10/2/201510/5/201510/5/2015 9:16:18 AMAPART
Partial final life fire safety passed/complete, contractor Tim, phone number ###-####, will schedule a final inspection once all office furniture/fixtures are in place. One fire sprinkler head needs to be moved to accomidate new wall, currently fire sprinkler is spaced to far off of wall.
BLD15-03319 FIRE-Final Inspection10/2/201510/5/201510/5/2015 9:15:26 AMAPART
Partial final life fire safety passed/complete, contractor Tim, phone number ###-####, will schedule a final inspection once all office furniture/fixtures are in place.
BLD15-03301 FIRE-Final Inspection10/2/201510/5/201510/5/2015 9:13:50 AMAPART
Partial final life fire safety passed/complete, contractor Tim, phone number ###-####, will schedule a final inspection once all office furniture/fixtures are in place.
BLD15-00623 FIRE-Final Inspection10/2/201510/5/201510/5/2015 12:00:00 AMPCANC
Ross Phone #: ###-####