Inspections for the day of: Wednesday, October 5, 2016.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00641 INSP-Sprinkler Rough-in10/5/201610/5/201610/5/2016 2:55:27 PMPPART
24 hour air test for dry systems associated with this permit started at 11:00AM (Total of 7 dry systems in test for 24 hours)
FIR16-00341 INSP-Sprinkler Rough-in10/5/201610/5/201610/5/2016 2:55:13 PMPPART
24 hour air test for dry systems associated with this permit started at 11:00AM (Total of 7 dry systems in test for 24 hours)
FIR15-00602 INSP-Sprinkler Rough-in10/5/201610/5/201610/5/2016 2:54:58 PMPPART
24 hour air test for dry systems associated with this permit started at 11:00AM (Total of 7 dry systems in test for 24 hours)
BLD15-03137 FIRE-Final Inspection10/5/201610/5/201610/5/2016 2:51:23 PMPPASS
No fire sprinklers, no fire alarms, space is a vanilla TI unoccupied space so fire extinguishers are not required. Final life fire safety inspection passed/complete.
FIR15-00198 INSP-Alarm Testing10/5/201610/5/201610/5/2016 1:45:58 PMPCANC
Call prior to going Phone #: 2089411846 >> Inspection requested via mobile web by Brian A Inspection cancelled via mobile web on Wednesday, October 05, 2016.
BLD15-04452 FIRE-Final Inspection10/4/201610/5/201610/5/2016 12:38:51 PMAPASS
Fire department inspection is complete, this was the final item for life fire safety, final life fire safety inspection passed/complete.
FIR16-00593 INSP-Final Inspection10/5/201610/5/201610/5/2016 11:22:29 AMAPASS
Rough in inspection for overhead fire sprinkler piping complete. Final fire sprinkler inspection passed/complete.
FIR16-00582 INSP-Final Inspection10/5/201610/5/201610/5/2016 11:22:10 AMAPASS
Rough in inspection for overhead fire sprinkler piping complete. Final fire sprinkler inspection passed/complete.
FIR16-00572 INSP-Final Inspection10/4/201610/5/201610/5/2016 11:21:19 AMAPASS
Final fire alarm inspection passed/compete
FIR16-00571 INSP-Final Inspection10/4/201610/5/201610/5/2016 11:21:02 AMAPASS
Final fire alarm inspection passed/compete
BLD16-01000 FIRE-Final Inspection10/4/201610/5/201610/5/2016 11:18:06 AMAPASS
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIR16-00473 INSP-Sprinkler Rough-in10/5/201610/5/201610/5/2016 9:19:15 AMPPASS
Underground main supply approved for cover.
BLD16-01838 FIRE-Final Inspection10/4/201610/5/201610/5/2016 8:52:01 AMAPASS
Final fire sprinkler inspection for area of work complete, final fire alarm inspection for area of work complete, final commercial hood fire suppression system inspection complete, fire sprinkler riser room was locked so I did not verify if fire sprinkler system inspection is current, fire extinguishers have current inspection tags and will be mounted in discussed locations. Final life fire safety inspection passed/complete.
FIR16-00620 INSP-Final Inspection10/4/201610/5/201610/5/2016 8:48:32 AMAPASS
Final fire alarm inspection passed/complete
FIR16-00630 INSP-Final Inspection10/4/201610/5/201610/5/2016 8:47:13 AMAPASS
Final commercial hood fire suppression system inspection complete.
BLD16-01838 FIRE-Alarm Testing10/4/201610/5/201610/5/2016 8:43:51 AMADONE
Alarm testing complete
BLD16-01484 FIRE-Final Inspection10/4/201610/5/201610/5/2016 7:53:00 AMAPASS
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are in common area's with current inspection tags, final life fire safety inspection passed/complete.