Inspections for the day of: Monday, October 6, 1997.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorWes Worcester
TitleBLD-COM/RES INSPECTOR
Phone #340-1490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC97-02742 INSP - Gas log/ Fireplace10/3/199710/6/199710/6/1997 12:00:00 AMACANC
GIVEN TO ALLEN
BLD97-02090 INSP - Energy code compliance10/6/199710/6/199710/6/1997 12:00:00 AMAPASS
BLD97-02452 INSP - Final10/3/199710/6/199710/6/1997 12:00:00 AMAPASS
9 AM
BLD97-02601 INSP - Footings10/6/199710/6/199710/6/1997 12:00:00 AMANR
STILL PLACING REBAR
BLD97-02212 INSP - Footings10/6/199710/6/199710/6/1997 12:00:00 AMPPART
PLAN SHOWS A KEYWAY IN GARAGE FTG....ASKED BLDR TO RESPOND AS IT IS NOT INSTALLED.
BLD97-02452 INSP - Letter of compliance10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
C/C ISSUED
BLD97-02601 INSP - Footings10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
SAYS TO REMIND YOU OF 1:30 APT. C/N POSTED AND ISSUES ANSWERED
BLD97-02104 INSP - Conference10/6/199710/6/199710/6/1997 12:00:00 AMPFAIL
STEED PROJECT MGR STATED THIS WAS A V-1HR BLDG WITH SPRINKLER SUBSTITUTION...? THEY WERE NOT READY FOR A FRAME INSP AND HAVE NUMEROUS PENETRATIONS IN A VN BLDG
BLD97-02104 INSP - Framing/Rough-in10/6/199710/6/199710/6/1997 12:00:00 AMPNR
NUMEROUS PENETRATIONS IN 1 HR CORRIDOR MEMBRANE WITH ROCKED COLUMNS, DUCT PENETRATIONS IN CEILING, CEILING NOT FRAMED COMPLETELY, NEED DETAILS FROM ARCHITECT FOR FIXES, VN BLDG
BLD96-01219 INSP - Energy code compliance10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
BLD96-01219 INSP - Framing/Rough-in10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
ALREADY COVERING LID AS PER C/N OK
BLD97-01349 INSP - Conference10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
WANTS TO USE WHITE VAPOR BARRIER IN UNFINISHED SPACE, TYP
BLD97-01349 INSP - Energy code compliance10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
BLD97-01545 INSP - Conference10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
MET W/TERRY RECORDS AND SUPER ON SITE
BLD97-01545 INSP - Site Preparation10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
2:30 APT. YOU MADE WITH HIM??????
BLD97-01828 INSP - Foundation10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
LAST SECTION OF FDN WALL POURED
BLD97-01828 INSP - Foundation10/6/199710/6/199710/6/1997 12:00:00 AMPNR
NEEDS 25" SPLICE ON REBAR LAPS....PLACING ADD BAR
BLD97-01828 INSP - Footings10/6/199710/6/199710/6/1997 12:00:00 AMPNR
IMBEDDED WOOD IN FTG NORTH SIDE...DO NOT BACKFILL UNTIL REMOVED AND APPROVAL BY INSPECTOR
BLD97-02090 INSP - Conference10/6/199710/6/199710/6/1997 12:00:00 AMPPASS
COMING DOWN TO SPLIT OUT DUPLEX INTO TOWNHOUSE PERMITS
BLD97-02212 INSP - Footings10/3/199710/6/199710/2/1997 12:00:00 AMACANC
CHANGED TO PM