FIR07-01042
| INSP-Sprinkler Rough-in/Hydro | 10/6/2008 | 10/6/2008 | 10/6/2008 4:44:12 PM | A | FAIL |
|
|
Inspection for the 1st floor failed due to field changes in pipe routing, head locations and floor plan layout in difference to the stamped approved plan set. Will need to provide accurate resubmittals for on site inspection prior to approval for ceiling cover.
|
FIR08-00516
| INSP-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 4:38:48 PM | A | CANC |
|
|
Bruce Phone #: ###-####
|
FIR08-00371
| INSP-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 4:37:59 PM | P | NH |
|
|
Bill Phone #: ###-#### NOTE: Contractor not available on site
|
FIR07-00928
| INSP-Sprinkler Rough-in/Hydro | 10/6/2008 | 10/6/2008 | 10/6/2008 4:36:22 PM | A | FAIL |
|
|
Inspection for the attic antifreeze system only. Field installation does not match approved plans at several locations including the design area, added heads, pipe routing, deleted heads, etc. Will need to provide approved resubmittals reflecting field modifications prior to cover. Also noted one unprotected cavity, a missing hanger, bushings at all branchline upright heads-circled locations on plans.
|
BLD08-01547
| FIRE-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 2:55:38 PM | A | PASS |
|
|
Fire life safety inspection passed. NOTE: Max occupant load signage at the two training/conference rooms to be posted as discussed-will verify at next site visit.
|
BLD08-01224
| FIRE-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 2:53:21 PM | A | PASS |
|
|
Fire life safety passed.
|
FIR08-00610
| INSP-Final Inspection | 10/6/2008 | 10/6/2008 | 10/6/2008 2:52:12 PM | P | PASS |
|
|
Noted deficiencies corrected, storage room spacing adjusted, fire sprinkler permit finaled.
|
FIR08-00597
| INSP-Final Inspection | 10/6/2008 | 10/6/2008 | 10/6/2008 2:50:54 PM | P | PASS |
|
|
Fire sprinkler permit final inspection passed.
|
BLD07-03163
| FIRE-Final Inspection | 10/6/2008 | 10/6/2008 | 10/6/2008 2:47:39 PM | A | PART |
|
|
Items needed prior to permit fire life safety final include repair one EM exit discharge light at the main entry, spin the SW hydrant 180 deg. to face the building, provide one fire extinguisher at the cylinder pick/sort area #132 when racking is installed, the spray booth fire sprinkler permit work needs to be completed inspected and approved, noted work at the fuel island is not finished at this time. Recieved signed letter from Musgrove Engineering regarding gas control system functionality per design requirements. Okay to begin equipment installation per agreements on file.
|
BLD07-03163
| FIRE-Alarm Testing | 10/6/2008 | 10/6/2008 | 10/6/2008 2:33:15 PM | A | DONE |
|
|
Duplicate inspection request.
|
FIR08-00289
| INSP-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 2:32:03 PM | A | PASS |
|
|
Three C/N items repaired, forward flow testing completed acceptable, fire sprinkler permit finaled.
|
FIR08-00278
| INSP-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 2:30:12 PM | A | PART |
|
|
Correction items per last inspection verified for completion, alarm testing passed, permit finaled.
|
FIR08-00424
| INSP-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 10:30:36 AM | A | NR |
|
|
Equipment is not yet installed, permit work not completed for inspection at this time.
|