Inspections for the day of: Monday, October 6, 2014.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-01744 FIRE-Conference10/6/201410/6/201410/6/2014 3:34:56 PMPDONE
Provide exit signs/emergency lights/exit discharge lights and annual inspection for the fire extinguishers as discussed. The existing daycare fire alarm system will not need to be extened into the new Foyer/Restroom per Scott and I's discussion. Rob Phone #: ###-####
BLD13-03351 FIRE-Final Inspection10/6/201410/6/201410/6/2014 3:04:56 PMPPASS
Life safety passed
FIR14-00495 INSP-Sprinkler Rough-in/Hydro10/3/201410/6/201410/6/2014 2:37:29 PMPPASS
Overhead rough-in and overhead hydro tests passed. Piping can not be covered until a tenting inspection has been performed.
FIR14-00461 INSP-Supply line flush10/3/201410/6/201410/6/2014 2:36:24 PMPFAIL
Tried to flush the underground but the water was not turned on.
FIR14-00356 INSP-Final Inspection10/6/201410/6/201410/6/2014 2:35:20 PMPPASS
Permit finaled
FIR14-00399 INSP-Sprinkler Rough-in10/6/201410/6/201410/6/2014 2:33:48 PMPFAIL
Piping has been covered with out a tenting inspection. I was provided access through an access panel and found exposed piping. Sheet rock will need to be removed
FIR14-00650 INSP-Final Inspection10/6/201410/6/201410/6/2014 2:19:02 PMPPASS
permit finaled
FIR14-00555 INSP-Supply line flush10/3/201410/6/201410/6/2014 2:16:34 PMPPASS
Underground supply line flush passed