BLD13-00166
| BLD-Conference | 10/2/2014 | 10/3/2014 | | A | |
|
|
|
BLD14-00210
| BLD-Framing/Rough-in | 10/6/2014 | 10/6/2014 | 10/6/2014 4:09:57 PM | P | PASS |
|
|
Richard Phone #: ###-####
|
BLD14-01509
| BLD-Energy code compliance | 10/6/2014 | 10/6/2014 | 10/6/2014 3:20:25 PM | P | NR |
|
|
Pat Phone #: ###-####. Needs tenting inspection.
|
BLD14-02404
| BLD-Conference | 10/6/2014 | 10/6/2014 | 10/6/2014 2:53:11 PM | P | DONE |
|
|
Phone #: ###-#### Inspection requested via web by Ira Rutledge
|
BLD14-02404
| DOC - Permit Finaled | 10/6/2014 | 10/6/2014 | 10/6/2014 2:52:36 PM | P | PASS |
|
|
Per contractor, installed per manufactuer recomendations and wii have manufactuer rep inspect.
|
BLD14-00819
| BLD-Conference | 10/5/2014 | 10/6/2014 | 10/6/2014 1:31:48 PM | P | PASS |
|
|
Framing re-inspection 1st Floor.
Call if locked up for the key code. ###-#### ###-####
Thanks,
Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All framing issues hace been resolved. Ok to insulate 1st. floor only.
|
BLD14-00210
| BLD-Framing/Rough-in | 10/3/2014 | 10/6/2014 | 10/6/2014 11:03:00 AM | A | NR |
|
|
Richard Phone #: ###-####
|
MIS14-00241
| BLD-Conference | 10/3/2014 | 10/6/2014 | 10/6/2014 9:53:22 AM | A | FAIL |
|
|
Christina. Abuilding permit is required for new siding, possible addition to se corner of existing house and posiible re-roof.
|
BLD13-02587
| BLD-Final | 10/3/2014 | 10/6/2014 | 10/6/2014 8:40:42 AM | A | PASS |
|
|
Call prior to going Phone #: 8016338210 >> Inspection requested via mobile web by Thomas Nielson. ok for perm occ.
|