FIR13-00065
| FIR-Aging Inspection | 10/6/2015 | 10/6/2015 | 10/13/2015 1:54:00 PM | | NR |
|
|
Should be called in by the end of the week
|
FIR15-00657
| INSP-Sprinkler Rough-in/Hydro | 10/5/2015 | 10/6/2015 | 10/6/2015 2:50:22 PM | P | CANC |
|
|
Wrong address called in
|
FIR15-00656
| INSP-Sprinkler Rough-in/Hydro | 10/5/2015 | 10/6/2015 | 10/6/2015 2:44:20 PM | P | CANC |
|
|
Not ready for hydro test
|
FIR15-00655
| INSP-Sprinkler Rough-in/Hydro | 10/5/2015 | 10/6/2015 | 10/6/2015 2:35:02 PM | P | PASS |
|
|
Above ground hydro test passed.
|
FIR15-00640
| INSP-Sprinkler Rough-in/Hydro | 10/6/2015 | 10/6/2015 | 10/6/2015 2:34:20 PM | P | FAIL |
|
|
Above ground hydro test failed due to visible loss on guage.
|
BLD14-03468
| FIRE-Final Inspection | 10/6/2015 | 10/6/2015 | 10/6/2015 1:38:48 PM | P | PART |
|
|
Given a temporary for life safety until the north exit discharge light to be repaired.
|
BLD14-03491
| FIRE-Final Inspection | 10/6/2015 | 10/6/2015 | 10/6/2015 1:37:17 PM | P | PART |
|
|
Life safety will be ok to pass when BLD14-03468 is signed off.
|
BLD14-03492
| FIRE-Final Inspection | 10/6/2015 | 10/6/2015 | 10/6/2015 1:36:20 PM | P | PART |
|
|
Life safety will be ok to pass when BLD14-03468 is signed off.
|
BLD14-03490
| FIRE-Final Inspection | 10/6/2015 | 10/6/2015 | 10/6/2015 1:35:03 PM | P | PART |
|
|
Life safety will be ok to pass when BLD14-03468 is signed off.
|
FIR15-00177
| INSP-Final Inspection | 10/5/2015 | 10/6/2015 | 10/6/2015 11:47:51 AM | A | PASS |
|
|
Permit finaled
|
FIR15-00250
| INSP-Final Inspection | 10/6/2015 | 10/6/2015 | 10/6/2015 11:45:22 AM | P | PASS |
|
|
Permit finaled
|
BLD15-01632
| FIRE-Final Inspection | 10/5/2015 | 10/6/2015 | 10/6/2015 8:46:24 AM | A | PART |
|
|
A temporary for fire life safety is being given until the possibly related vanilla finsh with Sundance Construction has been finaled or verified that it is not associated with this project.
|