Inspections for the day of: Tuesday, October 6, 2015.
Number of inspections: 27
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00024 General Inspection10/6/201510/6/201510/7/2015 2:56:29 PM PASS
WIP. Sidewalks and gutters are clean. Wattles installed at bottom of disturbed slope. No discharges offsite or uncontained trash/materials. No corrections issued.
ESC14-00719 General Inspection10/5/201510/6/201510/6/2015 4:03:15 PMPPASS
WIP. Perimeter is barricaded and surrounded by curbing. Vertical frame work is in progress. No significant trackout from site or laydown yards observed. No corrections issued.
ESC15-00044 Aging Inspection10/6/201510/6/201510/6/2015 3:44:12 PM PASS
Minor demo work has occured inside building. No materials or debris outside of building. No earthwork or utility work in ROW occuring. BLD not yet issued.
ESC15-00472 Aging Inspection10/6/201510/6/201510/6/2015 3:24:40 PM PASS
Work complete. All permits finaled. No ESC issues at industrial site. Pad prepped for future use.
ESC15-00472 DOC - Permit Finaled10/6/201510/6/201510/6/2015 3:24:05 PMPPASS
ESC15-00266 Aging Inspection10/6/201510/6/201510/6/2015 3:10:52 PM PASS
WIP on interior woodwork, finishes and appliance installations. Trash container bins still on site. All landscaping and site paving is complete. No violations observed.
ESC15-00035 General Inspection10/6/201510/6/201510/6/2015 2:34:51 PM PASS
Construction complete; revegetation and stabilization of newly graded parcels adjacent to roadway in progress. Temp BMP silt fence is still installed. No corrections.
ESC15-01032 Site Preparation10/6/201510/6/201510/6/2015 2:12:11 PMPPASS
Brett Phone #: ###-####

Approved for construction. Drop Zone sub BMPs installed. Site on Abrams in process of being cleaned as requested 10/5.
ESC15-00971 Tracking Control10/6/201510/6/201510/6/2015 1:38:06 PMPFAIL
Trackout and loose sediment runoff from site to Woodland Street. Receiving DI bag at corner of Woodland and Kimball has come unattached and is now ineffective.

Verbal CN issued via phone to TKO homes to sweep up site and do maintenance or replacement of DI bag.
ESC15-01187 Site Preparation10/6/201510/6/201510/6/2015 1:30:24 PMPPASS
Clarence Phone #: ###-####

Permit sign posted. Active projects on block by Evergreen Homes are in compliance. Previously installed DI bag that receives runoff from this site has near full capacity.

Approved to start. RP notified.
ESC15-01301 Site Preparation10/6/201510/6/201510/6/2015 1:05:21 PMPPASS
would like call ahead; Alex Phone #: ###-####

Site inspection with GC, homeowner is RP. Pre-fabricated garage structure to be assembled. Limited excavation, actually bringing in fill for elevation above flood plain. Work is over 50 ft from canal/5 mile creek which is heavily vegetated with trees, bushes, and grass that is to be undisturbed.

Permit sign posted at entrance to back yard. Reviewed ESC conditions with GC. Approved for construction.
ESC15-00619 Tracking Control10/6/201510/6/201510/6/2015 12:17:58 PMPFAIL
Correction needed:

Sweep up all trackout from recent activity in front of home on street and gutter.

Verbal request issued to Dave Wipple of Canyon Crest homes.
ESC15-01182 Site Preparation10/5/201510/6/201510/6/2015 11:45:34 AMPPASS
Dave Phone #: ###-####

BMPs installed. Permit sign posted. Current Canyon Crest homes in compliance with ESC conditions. Approved.
ESC15-01075 General Inspection10/6/201510/6/201510/6/2015 11:29:07 AMPPASS
WIP. Perimeter wattles installed. Permit sign posted. No trackout or discharges. Approved.
ESC14-00572 General Inspection10/6/201510/6/201510/6/2015 11:12:24 AM PASS
ESC15-00234 Aging Inspection10/6/201510/6/201510/6/2015 10:56:53 AM PASS
Temp BMPs installed, revegetation in progress. No corrections at this time.
ESC15-00468 Site Preparation10/5/201510/6/201510/6/2015 10:27:52 AMAPASS
Jason Phone #: ###-####

Permit sign posted with contact information and ESC #. RP on site for walk through. Tree cutting in progress.

Steep hillside site, plan is to preserve as much vegetation as possible. Dirt will be backfill at bottom of house and at that time (next week) plan is to install wire backed silt fence. Inspection is scheduled. Crane Creek (currently dry) is a toe of slope. Buffer will be approx. 40-50 ft...

Approved to begin.
ESC15-00175 General Inspection10/6/201510/6/201510/6/2015 9:22:30 AM PASS
Aberdeen Unit complete and occupied. Open areas cleaned, landscaped, and stabilized. Final site clean up in progress and covered under main Aberdeen permit. No further ESC inspections for this permit.
ESC15-00175 DOC - Permit Finaled10/6/201510/6/201510/6/2015 9:21:57 AMPPASS
ESC15-00174 General Inspection10/6/201510/6/201510/6/2015 9:21:23 AM PASS
Aberdeen Unit complete. Open areas cleaned and stabilized. Final site clean up in progress. No further ESC inspections for this permit.
ESC15-00174 DOC - Permit Finaled10/6/201510/6/201510/6/2015 9:21:15 AMPPASS
ESC15-00173 General Inspection10/6/201510/6/201510/6/2015 9:20:54 AM PASS
Aberdeen Unit complete. Open areas cleaned and stabilized. Final site clean up in progress. No further ESC inspections for this permit.
ESC15-00173 DOC - Permit Finaled10/6/201510/6/201510/6/2015 9:20:46 AMPPASS
ESC15-00172 General Inspection10/6/201510/6/201510/6/2015 9:20:35 AM PASS
ESC15-00171 General Inspection10/6/201510/6/201510/6/2015 9:20:20 AM PASS
Aberdeen Unit complete. Open areas cleaned and stabilized. Final site clean up in progress. No further ESC inspections for this permit.
ESC15-00172 DOC - Permit Finaled10/6/201510/6/201510/6/2015 9:20:12 AMPPASS
ESC15-00171 DOC - Permit Finaled10/6/201510/6/201510/6/2015 9:18:54 AMPPASS