Inspections for the day of: Friday, October 6, 2017.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-02496 FIRE-Final Inspection10/6/201710/6/201710/6/2017 1:49:31 PMPFAIL
I met Ben with ESI on site and discussed the previously noted correction issues
FIR17-00433 INSP-Sprinkler Rough-in10/6/201710/6/201710/6/2017 1:13:01 PMPPART
Rough-in passed for the lower level except the earthquake bracing needs to be possibly modified as discussed and siesmic bracing for the branchlines added. The sidewall heads, cooler heads and all of the upper/roof level heads have not been installed yet. No small documents were provided just the plans/piping layout. Riser is not built yet.
BLD17-01219 FIRE-Final Inspection10/5/201710/6/201710/6/2017 10:52:21 AMAPASS
Life safety passed
BLD17-00744 FIRE-Final Inspection10/5/201710/6/201710/6/2017 9:52:57 AMAPASS
Life safety passed.

Doug, will meet you at the compass Phone #: ###-####
FIR17-00266 INSP-Final Inspection10/5/201710/6/201710/6/2017 9:18:46 AMAPASS
Permit finaled
FIR17-00266 INSP-Sprinkler Rough-in10/5/201710/6/201710/6/2017 9:18:24 AMAPASS
Piping has been removed
FIR17-00545 INSP-Sprinkler Rough-in10/5/201710/6/201710/6/2017 8:16:58 AMAPASS
See the city approved plans for heads marked "ok", in the hardlids, where piping is ok to cover. Fitter did not have small documents.

Contact Brad Westbrook - ###-####
BLD17-02496 FIRE-Conference10/5/201710/6/201710/6/2017 7:43:06 AMADONE
Matt and I went through the life safety. Will need to test the emergency lights and exit signs. Also the existing fire alarm system will need to be extended/modified in the remodeled space as per discussion.

Matt Phone #: ###-####
NAF17-00066 INSP-Final10/3/201710/6/201710/6/2017 12:00:00 AMAPASS
Call prior to going Phone #: 2084845921 >> Inspection requested via mobile web by Cody-as per Troy Cobbley Final passed and to doc final
NAF17-00038 INSP-Final10/5/201710/6/201710/6/2017 12:00:00 AMAPASS
Phone #: 8014559121 >> Inspection requested via mobile web by Doug-as per Troy Cobbly-permit passes it's final so we need to doc final it
BLD17-01088 FIRE-Final Inspection10/5/201710/6/201710/5/2017 2:40:52 PMPPART
O.R. 141 life safety is passed. Sprinkler and alarm work is complete

Charles Miller Phone #: ###-####