Inspections for the day of: Monday, October 7, 2002.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRick Jackson
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR02-00130 INSP-Final Inspection10/4/200210/7/200210/7/2002 12:00:00 AMAPART
to mainly review cleanroom walls and protection under ducts. Jonathon Lee foreman on site; Phone #: ###-#### Internet Inspection Request from: Trent Bice okay per plans; need info on work in corridor used for tool wipe down area; EQ on main riser to wall 10/7/2002 3:04:05 PM
BLD02-01762 FIRE-Final Inspection10/4/200210/7/200210/7/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 10/04/2002 at 16:23:11. Contact: ###-####. door hardware; closures on basement and 2nd floor doors per plans 10/7/2002 10:59:47 AM
FIR02-00262 INSP-Final Inspection10/7/200210/7/200210/7/2002 12:00:00 AMAPASS
FIR02-00261 INSP-Final Inspection10/7/200210/7/200210/7/2002 12:00:00 AMAPASS
FIR02-00306 INSP-Final Inspection10/7/200210/7/200210/7/2002 12:00:00 AMAPASS
FIR02-00398 INSP-Final Inspection10/7/200210/7/200210/7/2002 12:00:00 AMAPASS
BLD02-01130 FIRE-Sprinkler Rough-in10/7/200210/7/200210/7/2002 12:00:00 AMPPART
okay to cover
BLD01-00398 FIRE-Conference10/7/200210/7/200210/7/2002 12:00:00 AMPPART
###-#### met with Dennis Holmes; Micron wants to use an alternate route for transporting HPM while the pass through is closed during the remodel; told Dennis that he will need to go through Dave Miller for a varience 10/8/2002 6:36:23 AM
FIR02-00340 INSP-Sprinkler Rough-in10/7/200210/7/200210/7/2002 12:00:00 AMPPART
###-#### okay to cover 10/7/2002 3:01:46 PM