| BLD-Conference | 10/7/2003 | 10/7/2003 | 10/7/2003 12:00:00 AM | | DONE |
|
|
reviewed area for pour which is upper slab at street level which provides exiting from the stair tower. Rebar to be cleaned and steel for slab mat is on site. Exterior form which was existing has been removed and will be reset to encompass new steel mat. There is a question by the contractor about changing the section which is a pt slab to reinforced concrete. The original plan is for a pt slab and that is what has been approved. To change would require a plan modifcation and would have to go through the approval process. Work is in progress on this area, A meeting with all design team member should occur on the 8th.
|