Inspections for the day of: Friday, October 7, 2011.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-00862 FIRE-Final Inspection10/7/201110/7/201110/7/2011 3:57:13 PMPPASS
life safety passed
FIR11-00477 INSP-Final Inspection10/6/201110/7/201110/7/2011 3:30:34 PMACANC
Cancel per Jeremy at ###-####
FIR11-00242 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:24:19 PMPPASS
permit finaled.
FIR11-00274 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:07:01 PMPPASS
Permit finaled.
FIR11-00275 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:06:19 PMPPASS
Permit finaled.
FIR11-00276 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:05:47 PMPPASS
Permit finaled.
FIR11-00277 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:04:49 PMPPASS
Permit finaled.
FIR11-00279 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:04:29 PMPPASS
Permit finaled.
FIR11-00453 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:04:08 PMPPASS
Permit finaled.
FIR11-00278 INSP-Final Inspection10/7/201110/7/201110/7/2011 3:03:32 PMPPASS
Permit finaled.
FIR11-00095 INSP-Final Inspection10/6/201110/7/201110/7/2011 2:59:57 PMAPASS
Permit finaled
FIR11-00382 INSP-Final Inspection10/7/201110/7/201110/7/2011 2:59:40 PMPFAIL
Phone lines have been fixed. The sprinkler system interconnections (tamper switches, flow switches) tested ok and signals reported correctly.EOL voltages tested ok. The manual pull station is mounted too high and will need to be lowered.To finish the inspection the duct smoke detectors and elevator recall functions need to be tested. I found a door to a secured area on the second floor that shall meet the requirements of IFC 1008.1.4.4. The fire alarm plans need to be resubmitted showing this interconnected with the fire alarm panel as well as showing the correct flow switch and tamper switch counts. I also went over the map requirements for the facp with Clay.
BLD11-01119 FIRE-Final Inspection10/7/201110/7/201110/7/2011 1:02:03 PMAFAIL
I went over door hardware with the door hardware supplier. He is going to install lever hardware on the west door and leave automatic flush bolts on the inactive leaf. He will provide keyed on the nonrequired door on the northeast corner of the building.
FIR11-00382 INSP-Final Inspection10/7/201110/7/201110/7/2011 10:04:49 AMAFAIL
The phone lines on the fire alarm panel are not calling out on a primary line and a secondary line as required. Only one line is being used. Inspection stopped. No other items were tested.