Inspections for the day of: Friday, October 7, 2016.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00569 INSP-Sprinkler Rough-in10/7/201610/7/201610/7/2016 2:46:55 PMPPASS
See the second floor plans where I have notated with todays day the corridor system where piping can be covered.
BLD16-01286 FIRE-Final Inspection10/6/201610/7/201610/7/2016 1:57:44 PMAPASS
life safety passed
BLD16-01491 FIRE-Final Inspection10/6/201610/7/201610/7/2016 1:56:59 PMAPASS
life safety passed
BLD16-00641 FIRE-Final Inspection10/7/201610/7/201610/7/2016 10:15:14 AMPPASS
Life safety passed
FIR16-00373 INSP-Final Inspection10/6/201610/7/201610/7/2016 10:14:58 AMAPASS
Permit finaled
BLD16-00275 FIRE-Final Inspection10/6/201610/7/201610/7/2016 10:07:34 AMAPASS
Life safety passed
BLD16-00733 FIRE-Final Inspection10/6/201610/7/201610/7/2016 10:05:18 AMAFAIL
Need project related fire sprinkler permit finaled. Need smoke alarms relocated to more thant 3' from the bathroom doors.
FIR16-00417 INSP-Final Inspection10/6/201610/7/201610/7/2016 8:42:08 AMAFAIL
Need to secure the poly piping in the crawl space every 32" as discussed. The cpvc risers need to be with-in 1 1/2" of the wall as per available listing. Provide fire caulking in the closets as discussed.
FIR16-00581 INSP-Final Inspection10/4/201610/7/201610/7/2016 8:37:22 AMAPASS
Permit finaled