ELE07-00429
| ELE-Aging Inspection | 10/8/2008 | 10/8/2008 | 10/13/2008 3:51:28 PM | | DONE |
|
|
called contractor to schedule an inspection if they are ready, told to verify if ground lugs terminated to in light poles, no esc this project
|
ELE07-00375
| ELE-Aging Inspection | 10/8/2008 | 10/8/2008 | 10/13/2008 9:29:36 AM | | DONE |
|
|
see final, no esc this project
|
ELE08-01858
| Electrical Rough-In | 10/8/2008 | 10/8/2008 | 10/8/2008 4:07:54 PM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/8/2008 at 9:45:27 AM. Contact: ###-####. ric ok
|
ESC08-00572
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:55:03 PM | P | PASS |
|
|
looked ok
|
ESC07-00003
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:54:13 PM | P | PASS |
|
|
looked ok
|
ESC08-00421
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:53:10 PM | P | PASS |
|
|
looked ok
|
ESC06-01299
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:52:22 PM | P | PASS |
|
|
looked ok
|
ESC08-00539
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:51:21 PM | P | PASS |
|
|
looked ok
|
ESC08-00781
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:50:25 PM | A | PASS |
|
|
looked ok
|
ESC08-00212
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:49:37 PM | A | PASS |
|
|
looked ok
|
ESC07-00733
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:48:39 PM | A | PASS |
|
|
looked ok
|
ESC07-00199
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:47:38 PM | A | PASS |
|
|
looked ok
|
ESC08-00730
| General Inspection | 10/8/2008 | 10/8/2008 | 10/8/2008 3:43:37 PM | A | PASS |
|
|
looked ok
|
ELE08-02678
| Electrical Rough-In | 10/8/2008 | 10/8/2008 | 10/8/2008 3:42:19 PM | P | PASS |
|
|
contact" John Ostolasa - ceiling insp. late afternoon inspection if possible. Also please call before going so John can let you in Phone #: ###-#### Internet Inspection Request from: Deb Gooden ok to cover ceiling, no esc this project
|
ELE08-02738
| Rough-In Permanent Service | 10/8/2008 | 10/8/2008 | 10/8/2008 3:09:07 PM | P | PASS |
|
|
eric Phone #: ###-#### ric ok, p/s u/g n ok
|
ELE08-02719
| Final | 10/6/2008 | 10/8/2008 | 10/8/2008 2:37:30 PM | P | CANC |
|
|
Try to schedule after 3:330pm If you have any questions please contact Francis@###-#### or ###-#### Phone #: ###-#### Internet Inspection Request from: Andy Rose wrong type request see p/s
|
ELE08-02719
| Permanent Service | 10/8/2008 | 10/8/2008 | 10/8/2008 2:29:04 PM | P | PASS |
|
|
Try to schedule after 3:330pm If you have any questions please contact Francis@###-#### or ###-#### Phone #: ###-#### Internet Inspection Request from: Andy Rose p/s o/h rec ok, no esc this project
|
ELE07-02302
| Final | 10/8/2008 | 10/8/2008 | 10/8/2008 2:27:16 PM | P | PART |
|
|
Contact Steve Hess - area A final please Phone #: ###-#### Internet Inspection Request from: Deb Gooden signed t/o card for auditorium, area a, left correction notice that stage lighting must be programmed before final
|
ELE07-03307
| Electrical Rough-In | 10/8/2008 | 10/8/2008 | 10/8/2008 2:10:34 PM | P | PASS |
|
|
CONTACT: NEIL RAMSEY - ABOVE CEILING INSPECTION FOR THE EAST PORTION OF 4TH FLOOR Phone #: ###-#### Internet Inspection Request from: Deb Gooden ok to cover 4th floor floor ceilings
|
ELE08-02171
| Final | 10/8/2008 | 10/8/2008 | 10/8/2008 1:35:30 PM | P | FAIL |
|
|
stu Phone #: ###-#### met contractor, left correction notice, NEC 410.10(D) luminaires in shower area shall be listed for damp locations, BCC no violations shall be retained
|
ELE08-02619
| Final | 10/8/2008 | 10/8/2008 | 10/8/2008 1:32:32 PM | P | PASS |
|
|
Pat there were some details that we talked about before you went on vacation. This is the one that you said could be inspected without interior access. Thanks Phone #: ###-#### Internet Inspection Request from: Jamie Winters called contractor, ok to final, no esc this project
|
ELE08-01580
| Final | 10/7/2008 | 10/8/2008 | 10/8/2008 11:52:39 AM | A | CANC |
|
|
Final Inspection. Please call Rick Sendra @ ###-#### 30 minutes prior to inspection to gain entry. Phone #: ###-#### Internet Inspection Request from: Kristopher Wilson talked with contractor, will reschedule for am tomorrow
|
ELE08-02740
| Rough-In Permanent Service | 10/8/2008 | 10/8/2008 | 10/8/2008 11:39:11 AM | P | CANC |
|
|
ufer ground Phone #: ###-#### Internet Inspection Request from: Don Lustig wrong type request, see ri
|
ELE08-02740
| Electrical Rough-In | 10/8/2008 | 10/8/2008 | 10/8/2008 11:38:42 AM | P | PASS |
|
|
ufer ground Phone #: ###-#### Internet Inspection Request from: Don Lustig ok to pour concrete encased electrode
|
ELE08-02667
| Electrical Rough-In | 10/7/2008 | 10/8/2008 | 10/8/2008 11:16:43 AM | A | PASS |
|
|
butch Phone #: ###-####called left message left survey, NEC 210.52(D) shall provide receptacle within 3' of bath sink, 210.11(C)(3) bath receptacle shall be supplied by 20a circuit with no other outlets, 210.52(A)(1) receptacle shall be installed such that no point is over 6' from receptacle in wall line, ric ok, no green sticker left, talked with contractor
|
ELE08-02521
| Electrical Rough-In | 10/8/2008 | 10/8/2008 | 10/8/2008 10:41:08 AM | A | PASS |
|
|
Ceiling rough-in. Mid to late morning would be ideal. Phone #: ###-#### Internet Inspection Request from: Dan Wright ok to cover ceiling, no esc this project
|
ELE08-00376
| Electrical Rough-In | 10/7/2008 | 10/8/2008 | 10/8/2008 10:21:34 AM | A | PASS |
|
|
tom Phone #: ###-#### corrections made, ric ok, no esc this project
|
ELE08-01858
| Electrical Rough-In | 10/7/2008 | 10/8/2008 | 10/8/2008 9:50:46 AM | A | NH |
|
|
John Phone #: ###-#### called contractor, no access, left card
|
ELE08-02676
| Conference | 10/7/2008 | 10/8/2008 | 10/8/2008 9:33:22 AM | A | DONE |
|
|
Please meet Brian Keith at Property at 9 a.m. Wednesday. Thanks. Phone #: ###-#### Internet Inspection Request from: Clint Tate met contractor to review requirements to bring park up to code, no esc this project
|
ELE07-02082
| Conference | 10/7/2008 | 10/8/2008 | 10/8/2008 8:53:59 AM | A | DONE |
|
|
steve Phone #: ###-#### met with owner, talked about t/s and using existing direct burial cable from ipco to feed temp pole. Talked about if mounting secure for t/s, said would probably work as mounted
|
ELE08-02724
| Electrical Rough-In | 10/7/2008 | 10/8/2008 | 10/8/2008 8:28:35 AM | A | PASS |
|
|
Rocky- cover Phone #: ###-#### ric ok
|
ELE08-02732
| Electrical Rough-In | 10/7/2008 | 10/8/2008 | 10/8/2008 8:00:50 AM | A | PASS |
|
|
Requesting approval for wall cover in all office areas. Phone #: ###-#### Internet Inspection Request from: Lloyd Looney called contractor, ric ok walls only
|
ELE08-02738
| Electrical Rough-In | 10/8/2008 | 10/8/2008 | 10/8/2008 12:00:00 AM | P | DONE |
|
|
eric Phone #: ###-####
|