Inspections for the day of: Monday, October 8, 2012.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKimberly M. Johnson
TitleEROSION CONTROL
Phone #208-794-3958
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC11-00059 General Inspection10/8/201210/8/201210/9/2012 1:30:47 PM PASS
ESC10-00778 General Inspection10/8/201210/8/201210/9/2012 11:39:54 AM PART
Some washout on ground. Perimeter control in NE side installed and in good condition
ESC12-00361 Site Preparation10/8/201210/8/201210/8/2012 3:40:12 PM PASS
ESC12-00320 General Inspection10/8/201210/8/201210/8/2012 3:24:02 PM PASS
ESC12-00126 General Inspection10/8/201210/8/201210/8/2012 3:12:08 PM FAIL
Perimeter control needs corrected or final landscaping completed
ESC12-00690 Complaint Inspection10/8/201210/8/201210/8/2012 2:06:51 PMPPASS
Responded to dust complaint. No active construction occurring at time of inspection. Soil conditions dry and powdery, prone to dust. Discussed complaint with RP and preventative measures available. Will require improved construction entrance if complaints continue.
ESC11-00415 General Inspection10/8/201210/8/201210/8/2012 11:51:53 AM PASS
Landscape seeded and mulched. No vegetation yet.
ESC11-00117 General Inspection10/8/201210/8/201210/8/2012 11:34:59 AM PASS
ESC12-00032 General Inspection10/8/201210/8/201210/8/2012 11:27:23 AM FAIL
Construction refuse oveflowing, gutter needs swept, rills forming on slope in back. Part of backyard has been stabilized with sod. Slope track walked horizontally. Met with RP onsite. Slope stabilization scheduled for Friday, 10/12. Refuse called in to be hauled out this week. Crew onsite today will sweep gutter today.
ESC12-00898 Complaint Inspection10/8/201210/8/201210/8/2012 12:00:00 AMAPART
Complaint construction debri is entering unprotected inlet. Site visit found perimeter controls in place and one drain inlet installed. The adjacent drop inlet was not protected. No evidence of pollutants entering storm drain at the time of inspection. Called RP to request inlet protection in both drains. Will be complete by end of day 10/9