FIR14-00375
| INSP-Final Inspection | 10/7/2014 | 10/8/2014 | 10/8/2014 4:29:24 PM | P | PART |
|
|
Final pending outside bell, flow test per contractor.
|
FIR14-00377
| INSP-Sprinkler Rough-in/Hydro | 10/7/2014 | 10/8/2014 | 10/8/2014 4:05:19 PM | P | PART |
|
|
UG fire supply line and new overhead system both passed hydrostatic testing.
|
BLD14-02419
| FIRE-Final Inspection | 10/8/2014 | 10/8/2014 | 10/8/2014 4:03:54 PM | P | PASS |
|
|
C/n items finished with the exception of door hardware per plan at the second exit. This item to be completed prior to structural final and verified at that time per discussion. Fire life safety finaled.
|
FIR14-00728
| INSP-Sprinkler Rough-in | 10/8/2014 | 10/8/2014 | 10/8/2014 2:33:47 PM | P | PART |
|
|
UG fire supply line okayed for bury from the point of connection at the property line to approx. 135' out.
|
FIR14-00344
| INSP-Sprinkler Rough-in | 10/7/2014 | 10/8/2014 | 10/8/2014 2:31:47 PM | A | PART |
|
|
Inspection for joist space fire stopping at building B 3rd floor completed. Rough-in at the 4th floor area B 2" main also finished including branch line tie-ins to apartments units.
|
BLD14-01632
| FIRE-Conference | 10/8/2014 | 10/8/2014 | 10/8/2014 2:28:15 PM | A | DONE |
|
|
Regarding project completion schedule, fire life safety inspection items.
|