Inspections for the day of: Wednesday, October 8, 2014.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00375 INSP-Final Inspection10/7/201410/8/201410/8/2014 4:29:24 PMPPART
Final pending outside bell, flow test per contractor.
FIR14-00377 INSP-Sprinkler Rough-in/Hydro10/7/201410/8/201410/8/2014 4:05:19 PMPPART
UG fire supply line and new overhead system both passed hydrostatic testing.
BLD14-02419 FIRE-Final Inspection10/8/201410/8/201410/8/2014 4:03:54 PMPPASS
C/n items finished with the exception of door hardware per plan at the second exit. This item to be completed prior to structural final and verified at that time per discussion. Fire life safety finaled.
FIR14-00728 INSP-Sprinkler Rough-in10/8/201410/8/201410/8/2014 2:33:47 PMPPART
UG fire supply line okayed for bury from the point of connection at the property line to approx. 135' out.
FIR14-00344 INSP-Sprinkler Rough-in10/7/201410/8/201410/8/2014 2:31:47 PMAPART
Inspection for joist space fire stopping at building B 3rd floor completed. Rough-in at the 4th floor area B 2" main also finished including branch line tie-ins to apartments units.
BLD14-01632 FIRE-Conference10/8/201410/8/201410/8/2014 2:28:15 PMADONE
Regarding project completion schedule, fire life safety inspection items.