Inspections for the day of: Wednesday, October 8, 2014.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00721 INSP-Sprinkler Rough-in10/8/201410/8/201410/8/2014 3:36:34 PMPPASS
See the city approved plans for location of one of the two in building risers that has been installed and is ok to cover
FIR14-00471 INSP-Sprinkler Rough-in10/8/201410/8/201410/8/2014 3:29:46 PMPPASS
Rough-in passed on the existing piping area. Piping can be covered.
FIR14-00533 INSP-Sprinkler Rough-in10/7/201410/8/201410/8/2014 2:45:36 PMPPASS
Rough-in passed. Piping can not be covered until a tenting inspection has been performed.
BLD14-02865 FIRE-Final Inspection10/8/201410/8/201410/8/2014 2:44:25 PMPPART
Temporary occupancy per scope of work for Fire is approved. Owner has already started installing air lines and an air compressor.
FIR14-00494 INSP-Final Inspection10/7/201410/8/201410/8/2014 2:05:24 PMPPASS
Permit finaled
FIR14-00607 INSP-Final Inspection10/8/201410/8/201410/8/2014 2:02:46 PMPPASS
Permit finaled
FIR14-00466 INSP-Supply line flush10/7/201410/8/201410/8/2014 2:02:17 PMPPASS
Underground supply line flush passed
FIR14-00464 INSP-Supply line flush10/7/201410/8/201410/8/2014 10:29:34 AMAPASS
Underground flush passed
BLD14-02095 FIRE-Conference10/7/201410/8/201410/8/2014 9:53:46 AMADONE
I verified that the insulation was being installed in the entire space for the overbuild where the anti-freeze system has been removed and fire stopped to less that 1,000 cublc feet per compartment. Keith Phone #: ###-####