MEC01-01555
| Final | 10/8/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 10/08/2001 at 14:19:57. Contact: ###-####.
|
MEC01-02407
| Pressure Test | 10/8/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | PASS |
|
|
pres test?? monte- ###-#### 60# test on 2# piping only 10/9/2001 10:04:06 AM
|
MEC01-02925
| Rough-in | 10/8/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 10/08/2001 at 14:52:13. Contact: ###-####. c/n posted 10/9/2001 9:31:51 AM
|
MEC01-02925
| Pressure Test | 10/8/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/08/2001 at 14:52:28. Contact: ###-####.
|
MEC01-02944
| Rough-in | 10/8/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/08/2001 at 13:12:02. Contact: ###-####.
|
MEC01-02944
| Pressure Test | 10/8/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | FAIL |
|
|
pipe undersized at furn. wh 10/9/2001 9:12:53 AM
|
MEC01-01346
| Pressure Test | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | CANC |
|
|
Scheduled by Inspector: 350 On 10/9/2001 8:45:30 AM
|
MEC01-01348
| Pressure Test | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 350 On 10/9/2001 8:47:18 AM
|
MEC01-01348
| Final | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 350 On 10/9/2001 10:32:45 AM
|
MEC01-02859
| Final | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | P | FAIL |
|
|
no answer 10/9/2001 1:54:49 PM
|
MEC01-03011
| Pressure Test | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | P | FAIL |
|
|
not as per plans, black pipe in dirt, redo and new test on med. side, low side not done 10/9/2001 2:38:56 PM
|
MEC01-03012
| Rough-in | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | P | PASS |
|
|
todd- ###-####
|
MEC01-03014
| Rough-in | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | P | PASS |
|
|
todd ###-####
|
MEC01-02506
| Final | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/09/2001 at 09:49:56. Contact: ###-####.
|
MEC01-02804
| Pressure Test | 10/8/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | P | CANC |
|
|
pres test ###-#### -darren
|
MEC01-01103
| Pressure Test | 10/9/2001 | 10/9/2001 | 10/9/2001 12:00:00 AM | P | PASS |
|
|
###-####
|