Inspections for the day of: Wednesday, October 9, 2013.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBill VanDegrift
TitlePLM-INSPECTOR
Phone #794-9372
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC13-04156 Conference10/8/201310/9/201310/10/2013 1:38:04 PMPPASS
Please call Paul Gibson@ ###-#### Prior to Inspection Phone #: ###-#### >> Inspection requested via web by Shannon Wells
MEC13-04172 Final10/9/201310/9/201310/9/2013 3:33:45 PMPPASS
Late afternoon please. Thanks. Phone #: ###-#### >> Inspection requested via web by April Thomas
GCP13-00141 GCP- Rough-in10/9/201310/9/201310/9/2013 3:01:45 PMPFAIL
Josh ###-#### no tests on, vent backgraded, update permit to a duplex,
GCM13-00246 GCM-Rough-in10/9/201310/9/201310/9/2013 2:54:29 PMPNR
Erin ###-#### provide access to acca report, access to equipment, update permit to a duplex, tie in fresh air
GCM13-00245 GCM-Rough-in10/9/201310/9/201310/9/2013 2:51:27 PMPNR
Erin ###-#### update permit to a duplex, provide access to equipment, provide acca report, connect fresh air
GCM13-00262 GCM-Rough-in10/9/201310/9/201310/9/2013 2:49:58 PMPNR
Erin ###-#### not built yet
GCM13-00261 GCM-Rough-in10/9/201310/9/201310/9/2013 2:44:48 PMPNR
Erin ###-#### not built yet
PLM13-02836 Plumbing Rough-in10/9/201310/9/201310/9/2013 1:16:09 PMPPASS
Please call Johny with questions ###-####. Thank you, Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala ri ok
MEC13-04072 Pressure Test10/4/201310/9/201310/9/2013 12:04:37 PMPPASS
gas pressure test miguel ###-#### Phone #: ###-#### >> Inspection requested via web by Dustin Rich 20# test ok
MEC13-04150 Rough-in10/9/201310/9/201310/9/2013 11:35:48 AMPPASS
ready for inspection. 2 fireplaces Phone #: ###-#### >> Inspection requested via web by Russ Curtis ri 20# 2-fp ok
MEC13-04054 Pressure Test10/8/201310/9/201310/9/2013 10:59:42 AMPPASS
Phone #: ###-#### >> Inspection requested via web by April Thomas ri 20# test ok
MEC13-04054 Rough-in10/8/201310/9/201310/9/2013 10:59:05 AMAPASS
Phone #: ###-#### >> Inspection requested via web by April Thomas ri 20# test ok
MEC13-02945 Final10/8/201310/9/201310/9/2013 10:15:07 AMPPASS
Marc ###-#### >> Inspection requested via web by Jason Robinson
MEC12-04109 Final10/8/201310/9/201310/9/2013 10:02:45 AMACANC
###-#### no fire place installed at this time per contractor
MEC12-04109 Final10/9/201310/9/201310/9/2013 10:01:59 AMPPASS
###-#### contractor said the owner wasn't happy with the fire place and it was removed. final as a gas test only
MEC13-04161 Final10/8/201310/9/201310/9/2013 9:37:19 AMACANC
Please call ahead for access - Dave Phone #: ###-#### will reschedule
MEC13-04161 Pressure Test10/8/201310/9/201310/9/2013 9:36:15 AMACANC
Please call ahead for access - Dave Phone #: ###-#### will reschedule
MEC13-02139 Final10/8/201310/9/201310/9/2013 9:31:06 AMAPASS
screens installed ready for final. Phone #: ###-#### >> Inspection requested via web by jack hester
MEC13-03958 Rough-in10/8/201310/9/201310/9/2013 8:45:54 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Randy Hart ri 20# test and db ok
MEC13-02540 Final10/8/201310/9/201310/9/2013 8:15:51 AMACANC
Thanks Dixie Phone #: ###-#### >> Inspection requested via web by Jennifer Roy not ready yet