FIR13-00497
| INSP-Sprinkler Rough-in | 10/9/2013 | 10/9/2013 | 10/9/2013 3:44:33 PM | P | PASS |
|
|
See the city approved plans for piping above hardlids that can be covered. Marked "ok" in red.
|
FIR13-00383
| INSP-Sprinkler Rough-in | 10/9/2013 | 10/9/2013 | 10/9/2013 3:35:06 PM | P | PART |
|
|
In general the rough-in passed. Noted missing retaining straps and a couple of earth quake braces. As-builts will be needed showing the changes in the main routing near the riser and the deletion of one of the 2" branchlines.
|
FIR12-00695
| INSP-Sprinkler Rough-in/Hydro | 10/8/2013 | 10/9/2013 | 10/9/2013 2:22:34 PM | A | PASS |
|
|
Overhead hydro passed
|
FIR13-00427
| INSP-Sprinkler Rough-in | 10/8/2013 | 10/9/2013 | 10/9/2013 2:21:56 PM | A | PASS |
|
|
Piping above hard lid is ok to cover.
|