ESC12-00893
| Aging Inspection | 10/9/2013 | 10/9/2013 | 10/9/2013 12:41:51 PM | | FAIL |
|
|
Called and left Rollo a voicemail explaining the entire Silt fence that runs along the northside of the site, as well as all other adjacent parcels needs to be either replaced or maintained by Friday 10-11-13 or a Stop Work Order will be placed for BMP Violation on all adjacent parcels. EEJ
|
ESC13-00495
| General Inspection | 10/9/2013 | 10/9/2013 | 10/9/2013 12:30:02 PM | | PART |
|
|
KJM placed notes saying "Final Stabilization will be established by October 2013". Contractors are now building on the two parcels, and are approximately 40% complete. Contacted Adam Lyman (RP) via cell phone to disclose this information and he stated he will contact me back after he finds out what is going on with progress.
|
ESC12-01109
| Aging Inspection | 10/9/2013 | 10/9/2013 | 10/9/2013 12:03:53 PM | | PASS |
|
|
|
ESC13-00521
| General Inspection | 10/9/2013 | 10/9/2013 | 10/9/2013 11:15:33 AM | | PART |
|
|
Revegetation not established on disturbed soils. Need Perminant Stabilization Initiated asap. Cannot locate RP's contact Number
|
ESC13-00471
| Stop Work Order | 10/7/2013 | 10/9/2013 | 10/9/2013 10:45:53 AM | A | FAIL |
|
|
Stop Work Order Issued Contacted Justin about BMP VIolations He stated they will cleanup concrete, install construction entrance, install perimeter BMP's and Sweep Street; Phone #: Justin:###-####
|
ESC13-00471
| BMP Violation | 10/9/2013 | 10/9/2013 | 10/9/2013 10:43:39 AM | P | FAIL |
|
|
BMP's Not Intalled as Contractor stated verbally onsite on 10-7-13. More construction took place during the stop work order.
|