Inspections for the day of: Wednesday, October 9, 2013.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEvan Jenkins
TitleEROSION CONTROL MANAGER
Phone #794-3958
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC12-00893 Aging Inspection10/9/201310/9/201310/9/2013 12:41:51 PM FAIL
Called and left Rollo a voicemail explaining the entire Silt fence that runs along the northside of the site, as well as all other adjacent parcels needs to be either replaced or maintained by Friday 10-11-13 or a Stop Work Order will be placed for BMP Violation on all adjacent parcels. EEJ
ESC13-00495 General Inspection10/9/201310/9/201310/9/2013 12:30:02 PM PART
KJM placed notes saying "Final Stabilization will be established by October 2013".
Contractors are now building on the two parcels, and are approximately 40% complete.
Contacted Adam Lyman (RP) via cell phone to disclose this information and he stated he will contact me back after he finds out what is going on with progress.
ESC12-01109 Aging Inspection10/9/201310/9/201310/9/2013 12:03:53 PM PASS
ESC13-00521 General Inspection10/9/201310/9/201310/9/2013 11:15:33 AM PART
Revegetation not established on disturbed soils. Need Perminant Stabilization Initiated asap.
Cannot locate RP's contact Number
ESC13-00471 Stop Work Order10/7/201310/9/201310/9/2013 10:45:53 AMAFAIL
Stop Work Order Issued
Contacted Justin about BMP VIolations
He stated they will cleanup concrete, install construction entrance, install perimeter BMP's and Sweep Street; Phone #: Justin:###-####
ESC13-00471 BMP Violation10/9/201310/9/201310/9/2013 10:43:39 AMPFAIL
BMP's Not Intalled as Contractor stated verbally onsite on 10-7-13.
More construction took place during the stop work order.