Inspections for the day of: Friday, October 9, 2015.
Number of inspections: 27
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00142 General Inspection10/9/201510/9/201510/12/2015 1:16:12 PM PASS
WIP. Foundation and concrete work for pool, home, and site walls is complete. Construction entrance is installed and no trackout.

Discussed erosion control on area below cement wall - rock chip material is to be installed below to protect the area and provide ground cover. RP-GC also noted that the cement wall will be painted/colored to match the hillside colors. No violations at site. No corrections issued at this time.
ESC15-00177 General Inspection10/9/201510/9/201510/12/2015 12:20:27 PM PASS
WIP. Street and sidewalk are clean. Workers parking on the street to prevent trackout. Hillside below rock retaining wall has had vegetation preserved and silt fence is installed. Some breaches in fence, but no sediment runoff occuring. Approved.
ESC14-00356 General Inspection10/9/201510/9/201510/12/2015 12:01:17 PM PASS
WIP on interior. No active earth work. No sediment runoff or significant trackout observed.

Trash and materials contained on site. Surround native vegetation has been preserved where possible. No corrections at this time, but will want to empty out the sediment bag at bottom of Ashtree soon, over 50% capacity.
ESC15-00411 Aging Inspection10/9/201510/9/201510/9/2015 4:00:13 PM PASS
Exterior construction complete. No disturbed area or issues. No further ESC inspections, permit finaled.
ESC15-00411 DOC - Permit Finaled10/9/201510/9/201510/9/2015 3:57:47 PMPPASS
ESC15-00481 Aging Inspection10/9/201510/9/201510/9/2015 3:49:03 PM PASS
Home complete, landscaped, and site cleaned up. No ESC corrections needed. Permit finaled.
ESC15-00481 DOC - Permit Finaled10/9/201510/9/201510/9/2015 3:48:23 PMPPASS
ESC15-00485 Aging Inspection10/9/201510/9/201510/9/2015 3:47:48 PM PASS
Home complete, landscaped, and site cleaned up. No ESC corrections needed. Permit finaled.
ESC15-00485 DOC - Permit Finaled10/9/201510/9/201510/9/2015 3:44:31 PMPPASS
ESC15-00371 Aging Inspection10/9/201510/9/201510/9/2015 3:35:55 PM PASS
Near completion. Yard landscaped and stabilized. Need to remove temp BMPs and trash container. No violations
ESC15-00107 General Inspection10/9/201510/9/201510/9/2015 3:03:17 PM PASS
ESC15-00702 Site Preparation10/9/201510/9/201510/9/2015 2:50:31 PMPPASS
Quinton Phone #: ###-####

BMPs installed include stabilized construction entrance at site exit, one way hauling traffic through site set up. Water truck on hand for fugitive dust control. Silt fence installed at northern boundary to treat any sheet flow. Permit posted on job trailer and SWPPP document is inside.

RP will install DI bag on King Street.

Approved
ESC14-00206 Random Inspection10/9/201510/9/201510/9/2015 11:47:18 AMPPASS
WIP on SFHs by Hayden Homes and Eagleridge in Sunnyridge phase 3. Streets appear to have been swept recently, new lined washout pit is installed and marked. DI bags installed. No windblown trash or fugitive dust issues occuring at time of inspection. Landscaping and irrigation line installation between roads and sidewalk is occuring, so some loose topsoil and dirt should be swept upon completion.

No corrections at this time..
ESC15-00677 Site Final10/9/201510/9/201510/9/2015 11:44:51 AMPPASS
Sunnyridge Eaglewood complete, landscaped, and occupied. Temp BMPs to remain installed for ongoing work in subdivision. ESC permit conditions satisfied.
ESC15-00714 Site Final10/9/201510/9/201510/9/2015 11:42:40 AMPPASS
Sunnyridge Hayden Home complete, landscaped, and occupied. Temp BMPs to remain installed for ongoing work in subdivision. ESC permit conditions satisfied.
ESC15-00665 Site Final10/9/201510/9/201510/9/2015 11:39:29 AMPPASS
Sunnyridge Hayden Home complete, landscaped, and occupied. Temp BMPs to remain installed for ongoing work in subdivision. ESC permit conditions satisfied.
ESC15-00672 Site Final10/9/201510/9/201510/9/2015 11:39:08 AMPPASS
Sunnyridge Hayden Home complete, landscaped, and occupied. Temp BMPs to remain installed for ongoing work in subdivision. ESC permit conditions satisfied.
ESC15-00752 Site Final10/9/201510/9/201510/9/2015 11:38:43 AMPPASS
Sunnyridge Hayden Home complete, landscaped, and occupied. Temp BMPs to remain installed for ongoing work in subdivision. ESC permit conditions satisfied.
ESC15-01149 Site Preparation10/8/201510/9/201510/9/2015 11:31:50 AMAPASS
Adam Phone #: ###-####

Permit sign posted. Sunnyridge BMPs installed (lined washout, DI sediment protection).

No issues with active Eagleridge homes. Approved.
ESC14-01119 General Inspection10/9/201510/9/201510/9/2015 11:12:43 AM PASS
Building complete, surrounding areas are stabilized and free of loose sediment or other materials. BLD near final stages. No ESC issues, no further ESC inspections.
ESC14-01119 DOC - Permit Finaled10/9/201510/9/201510/9/2015 11:11:43 AMPPASS
ESC15-00033 General Inspection10/9/201510/9/201510/9/2015 11:05:37 AM PASS
WIP on landscaping around perimeter of future car lot. Car lot is only partially paved, sales building is now fully erected and work ongoing in interior. Construction entrance is installed, though there is some trackout to Auto Drive.

Gratz Road and intersection with Auto Drive is also complete and has been swept. No trackout outside of Auto Mall, no discharges, fugitive dust or other issues observed. Approved.
ESC15-00521 Aging Inspection10/9/201510/9/201510/9/2015 10:52:35 AM PASS
TI complete. Site is clean and no loose sediment or unstabilized areas. ESC conditions satisfied.
ESC15-00521 DOC - Permit Finaled10/9/201510/9/201510/9/2015 10:52:01 AMPPASS
ESC15-00360 General Inspection10/9/201510/9/201510/9/2015 10:05:13 AM PASS
WIP on exterior and interior finishes. Earth work and frame are complete. No sediment trackout or runoff. Native vegetation around clearing limits has been preserved. Will need to stabilize area used for loading & parking off of Wind Dancer before final ESC inspection.
ESC14-00662 General Inspection10/9/201510/9/201510/9/2015 9:14:04 AM PASS
ESC15-00380 General Inspection10/9/201510/9/201510/9/2015 8:41:36 AM PASS
WIP at Breckenridge 4-plexes on vertical construction, interior wood work, and painting. No trackout or loose sediment being carried offsite. Boundary next to Maple Grove is bermed and has chain link fence. No violations observed.