FIR12-00604
| INSP-Sprinkler Rough-in | 11/1/2012 | 11/1/2012 | 11/2/2012 1:29:00 PM | P | PASS |
|
|
Tenting is complete. Piping is ok to cover.
|
FIR12-00543
| INSP-Final Inspection | 10/31/2012 | 11/1/2012 | 11/2/2012 1:25:57 PM | P | PASS |
|
|
Permit finaled
|
BLD12-00556
| FIRE-Final Inspection | 11/1/2012 | 11/1/2012 | 11/2/2012 9:27:01 AM | P | PASS |
|
|
life safety passed
|
BLD12-01694
| FIRE-Final Inspection | 10/31/2012 | 11/1/2012 | 11/2/2012 9:25:46 AM | A | PASS |
|
|
Permit finaled
|
FIR12-00513
| INSP-Sprinkler Rough-in | 10/31/2012 | 11/1/2012 | 11/1/2012 11:44:50 AM | A | PASS |
|
|
Rough-in passed. piping is ok to cover. Contractor needs to verify if the hangers need to meet NFPA 13 requirements for exceeding 100psi. Thiis applies to the modified heads. Also the pendant heads in the 9th floor conference room near the stairs are blocked by surface mount lights.
|
FIR12-00441
| INSP-Sprinkler Rough-in | 10/31/2012 | 11/1/2012 | 11/1/2012 11:30:01 AM | A | PASS |
|
|
underground flush passed inspection
|