Inspections for the day of: Thursday, November 1, 2012.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR12-00604 INSP-Sprinkler Rough-in11/1/201211/1/201211/2/2012 1:29:00 PMPPASS
Tenting is complete. Piping is ok to cover.
FIR12-00543 INSP-Final Inspection10/31/201211/1/201211/2/2012 1:25:57 PMPPASS
Permit finaled
BLD12-00556 FIRE-Final Inspection11/1/201211/1/201211/2/2012 9:27:01 AMPPASS
life safety passed
BLD12-01694 FIRE-Final Inspection10/31/201211/1/201211/2/2012 9:25:46 AMAPASS
Permit finaled
FIR12-00513 INSP-Sprinkler Rough-in10/31/201211/1/201211/1/2012 11:44:50 AMAPASS
Rough-in passed. piping is ok to cover. Contractor needs to verify if the hangers need to meet NFPA 13 requirements for exceeding 100psi. Thiis applies to the modified heads. Also the pendant heads in the 9th floor conference room near the stairs are blocked by surface mount lights.
FIR12-00441 INSP-Sprinkler Rough-in10/31/201211/1/201211/1/2012 11:30:01 AMAPASS
underground flush passed inspection