FIR13-00362
| INSP-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 4:27:13 PM | P | FAIL |
|
|
FA not ready.
|
FIR13-00379
| INSP-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 4:26:42 PM | P | FAIL |
|
|
FA system not ready. no pre test. doors not tied in. sprinkler system not tested
|
BLD13-00440
| FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 4:24:45 PM | P | FAIL |
|
|
FA system not ready. Doors not installed. No mag holders.
|
FIR13-00337
| INSP-Sprinkler Rough-in | 11/1/2013 | 11/1/2013 | 11/1/2013 2:26:44 PM | P | PASS |
|
|
spacing good, insulation good. OK to cover.
|
BLD13-02663
| FIRE-Final Inspection | 11/1/2013 | 11/1/2013 | 11/1/2013 11:20:21 AM | P | PASS |
|
|
Recieved information. Pass
|
BLD13-00979
| FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 11:15:44 AM | P | CANC |
|
|
Per James. Not ready
|
FIR13-00342
| INSP-Supply line flush | 11/1/2013 | 11/1/2013 | 11/1/2013 11:09:36 AM | P | CANC |
|
|
Per Mike, wants flush on Monday the 4th
|
FIR13-00439
| INSP-Supply line flush | 10/31/2013 | 11/1/2013 | 11/1/2013 10:27:48 AM | A | PART |
|
|
underground hydro only. no flush at this time. Hydro Pass. CDH
|
FIR13-00569
| INSP-Sprinkler Rough-in | 10/31/2013 | 11/1/2013 | 11/1/2013 10:26:42 AM | A | PART |
|
|
This is cover inspection for hanger installation only. L bracket hangers inspected and pass. ok to cover. no piping inspected. CDH
|
BLD13-03046
| FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 9:35:09 AM | A | PASS |
|
|
Good. No corections
|
BLD13-02663
| FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 9:34:40 AM | A | PART |
|
|
OK for building to inspect. I am waiting for the ASTM-E 85 paperwork for the carpet. Once its emailed to me I will sign permit off.
|
BLD13-02494
| FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 7:41:46 AM | A | CANC |
|
|
request 8:30 am // Jason Phone #: ###-####. Canceled by Jason 11/01
|