Inspections for the day of: Friday, November 1, 2013.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-00400 Aging Inspection11/1/201311/1/201311/1/2013 1:10:50 PM PASS
Work on detached garage is in progress. No ESC violations observed at time of inspection.
ESC13-00339 General Inspection11/1/201311/1/201311/1/2013 12:46:53 PM PASS
Parking lot has been mostly paved. DI protection on Elisa is satisfactory. Bare ground has had straw mulch placed on it. No corrections at this time. WIP.
ESC13-00465 General Inspection11/1/201311/1/201311/1/2013 11:26:09 AM PASS
Finaled.
ESC13-00465 DOC - Permit Finaled11/1/201311/1/201311/1/2013 11:25:50 AMPPASS
Retaining wall installed. ESC requirements have been met. Home construction is on different permit - see activity notes.
ESC13-00460 General Inspection11/1/201311/1/201311/1/2013 11:17:25 AM PASS
Finaled.
ESC13-00460 DOC - Permit Finaled11/1/201311/1/201311/1/2013 11:16:41 AMPPASS
House is complete, landscaped and stabilized. Slope behind house is stabilized with tacifyer. No corrections necessary, conditions met.
ESC13-00144 General Inspection11/1/201311/1/201311/1/2013 10:54:15 AM PASS
No changes or activity at site. Vegetation/stabilization in progress but not complete. Stockpile still on site. No track out. Will need to address stock pile before closing permit.
ESC13-00271 Aging Inspection11/1/201311/1/201311/1/2013 10:43:16 AM PART
Exterior of townhouse is complete, some interior work ongoing. Out front on Division a stormwater drainage structure is being trenched. No track out but no BMPs implement. Left message with RP to call and update project status/provide BMPs
ESC13-00272 Aging Inspection11/1/201311/1/201311/1/2013 10:42:17 AM PART
Exterior of townhouse is complete, some interior work ongoing. Out front on Division a stormwater drainage structure is being trenched. No track out but no BMPs implement. Left message with RP to call and update project status/provide BMPs
ESC13-00353 General Inspection11/1/201311/1/201311/1/2013 10:10:18 AM PASS
Finaled.
ESC13-00353 DOC - Permit Finaled11/1/201311/1/201311/1/2013 10:10:02 AMPPASS
House is complete, stabilized and landscaped. BLD permit already finaled. ESC conditions met. Somerset #5 sub still in development.
ESC12-00972 Tracking Control11/1/201311/1/201311/1/2013 9:37:05 AMAFAIL
Empty lot where subdivision wash out is needs construction entrance. Track out onto sidewalk, street and strip of porous concrete. Called RP to provide verbal correction notice.
ESC13-00312 Aging Inspection11/1/201311/1/201311/1/2013 9:26:03 AM PASS
Finaled.
ESC13-00312 DOC - Permit Finaled11/1/201311/1/201311/1/2013 9:25:45 AMPPASS
House is complete and landscaped. BLD permit has been finaled. No ESC corrections for this project. Adjacent lot being used by Laney Greens subdivision builders (Wood River).
ESC13-00313 Aging Inspection11/1/201311/1/201311/1/2013 9:23:49 AM PASS
Finaled.
ESC13-00313 DOC - Permit Finaled11/1/201311/1/201311/1/2013 9:23:27 AMPPASS
BLD permit has been finaled. House complete, landscaped, stabilized, and occupied. No ESC violations
ESC13-00125 General Inspection11/1/201311/1/201311/1/2013 9:18:19 AM PASS
Regrading and fill being placed in pond to raise elevation. Stockpiles still in use for project. No corrections at this time.
ESC13-00011 General Inspection11/1/201311/1/201311/1/2013 8:51:10 AM PASS
Lift station and related infrastructure is installed. BLD permit is open Other phases of 31st/Whitewater Blvd project are ongoing. No stabilization yet. No violations at this time.