Inspections for the day of: Thursday, November 12, 2009.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00352 Conference11/12/200911/12/200911/12/2009 10:28:45 PMADONE
River cuts will start to become closer to theriver is certain areas where drainage cells will be installed. Explained to the developer and the contractor over stabilizing and protecting the areas where all cut will occur.

Explained to the contractor over certain requirements prior to the start of the work at the south east end of project. Must develope and submit to the city an ammendment to the erosion control plan and give a schedule of the scope of work that will be completed.
ESC09-00093 General Inspection11/12/200911/12/200911/12/2009 3:47:27 PMPFAIL
Verbal to RP:
Post ESC sign where visable from the street.
Must stabilize all bare soil prior to finaling permit.
ESC07-01368 Aging Inspection11/12/200911/12/200911/12/2009 2:32:30 PM DONE
ESC07-01368 DOC - Permit Finaled11/12/200911/12/200911/12/2009 2:32:21 PMPPASS
ESC09-00181 Tracking Control11/12/200911/12/200911/12/2009 2:30:20 PMPFAIL
Correction Notice:
1.Clean up all sediment and debris off of all hard surfaces.
2.Maintain construction exit.
3. Post ESC sign where it is visable from Gowen Rd.
Failure to comply will result in a Stop Work Order. Will re-inspect on 11/13/09 PM
ESC09-00187 Tracking Control11/12/200911/12/200911/12/2009 2:29:29 PMPFAIL
Correction Notice:
1.Clean up all sediment and debris off of all hard surfaces.
2.Maintain construction exit.
3. Post ESC sign where it is visable from Gowen Rd.
Failure to comply will result in a Stop Work Order. Will re-inspect on 11/13/09 PM
ESC09-00186 Tracking Control11/12/200911/12/200911/12/2009 2:28:34 PMPFAIL
Correction Notice:
1.Clean up all sediment and debris off of all hard surfaces.
2.Maintain construction exit.
3. Post ESC sign where it is visable from Gowen Rd.
Failure to comply will result in a Stop Work Order. Will re-inspect on 11/13/09 PM
ESC09-00184 Tracking Control11/12/200911/12/200911/12/2009 2:28:13 PMPFAIL
Correction Notice:
1.Clean up all sediment and debris off of all hard surfaces.
2.Maintain construction exit.
3. Post ESC sign where it is visable from Gowen Rd.
Failure to comply will result in a Stop Work Order. Will re-inspect on 11/13/09 PM
ESC09-00182 Tracking Control11/12/200911/12/200911/12/2009 2:27:45 PMPFAIL
Correction Notice:
1.Clean up all sediment and debris off of all hard surfaces.
2.Maintain construction exit.
3. Post ESC sign where it is visable from Gowen Rd.
Failure to comply will result in a Stop Work Order. Will re-inspect on 11/13/09 PM
ESC09-00709 Site Preparation11/12/200911/12/200911/12/2009 1:56:15 PM PART
Move ESC sign to front of lot visable from the street. Relocated during the inspecton.
ESC09-00711 Site Preparation11/12/200911/12/200911/12/2009 1:42:13 PM PASS
ESC09-00721 Site Preparation11/12/200911/12/200911/12/2009 9:48:21 AMAPASS
Told RP and also ther PD that prior to any dewater activies occuring that they must submit a dewatering plan to the city and recieve an approval on the plan prior to the activity occuring. Will re-inspect on 11/16/09AM.
ESC09-00721 INSP - Stop Work Order11/12/200911/12/200911/12/2009 9:45:15 AMAPASS
Stop work order put in place due to working without a city ESC permit on 11/09/09. Permit has been issued. Stop work order has been lifted. All EC provisions are in place and actively working.
ESC09-00686 Site Preparation11/6/200911/12/200911/10/2009 1:20:27 PMAPASS