Inspections for the day of: Monday, November 13, 2006.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00425 INSP-Sprinkler Rough-in11/13/200611/13/200611/14/2006 10:21:49 AMPPART
OH hydrostatic test of floors 5 and 7-10 completed satisfactory. The 6th floor failed due to a broken guage.
BLD06-02487 FIRE-Final Inspection11/13/200611/13/200611/14/2006 9:09:39 AMPFAIL
Need to provide exit signs as indicated on plan review at two locations as discussed, door hardware at one meeting room will need to be changed, the project related fire sprinkler permit must be finaled.
FIR06-00808 INSP-Final Inspection11/13/200611/13/200611/14/2006 9:07:35 AMPFAIL
Two heads in confrence room 102 are overspaced.
FIR06-00783 INSP-Final Inspection11/13/200611/13/200611/14/2006 9:06:30 AMPPASS
Fire alarm permit finaled.
FIR06-00751 INSP-Final Inspection11/13/200611/13/200611/13/2006 3:33:38 PMPCANC
As late in the day as possible please Internet Inspection Request from: Terry Owsley Inspection cancelled from web by: Terry Owsley
FIR06-00424 INSP-Final Inspection11/13/200611/13/200611/13/2006 3:10:00 PMPPASS
Fire sprinkler permit finaled.
FIR06-00422 INSP-Final Inspection11/13/200611/13/200611/13/2006 3:09:36 PMPPASS
Fire sprinkler permit finaled.
FIR06-00423 INSP-Final Inspection11/13/200611/13/200611/13/2006 3:07:23 PMPNR
Final pending field ceiling tile install.
BLD04-00945 FIRE-Sprinkler Rough-in11/10/200611/13/200611/13/2006 3:06:38 PMAPART
The remainder of 3rd floor is okay to cover, tenting is satisfactory.
FIR06-00437 INSP-Final Inspection11/9/200611/13/200611/13/2006 1:20:45 PMAPASS
Fire alarm work is satisfactory, inspection passed.
FIR06-00629 INSP-Sprinkler Rough-in11/8/200611/13/200611/13/2006 1:17:25 PMAPART
OH rough-in is okay to cover except at the main and branch line tie in locations, two drops are not complete, underfloor sprinklers are acceptable.
BLD05-03415 FIRE-Final Inspection11/9/200611/13/200611/13/2006 10:40:27 AMAPASS
Fire life safety passed inspection.
FIR06-00639 INSP-Sprinkler Rough-in/Hydro11/9/200611/13/200611/13/2006 10:26:58 AMANR
OH hydrostatic test of the 3rd floor is not ready. 1st floor rough-in of the model unit for cover is okay. Discussed DSW locations at the 3rd floor canopies.