Inspections for the day of: Friday, November 13, 2009.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00518 INSP-Final Inspection11/12/200911/13/200911/13/2009 2:50:18 PMAFAIL
The scope of work for this permit has been completed. However this permit will not be finaled until the lack of freezing protection for the existing system has been addressed. I have contacted Scott Arelleno and left a voice message for Jerry McAdams in the fire dept. Upon confirmation that Jerry and the building owner are working on this problem I will proceed with finaling the permit.
FIR09-00281 INSP-Supply line flush11/11/200911/13/200911/13/2009 2:43:38 PMAPASS
The underground flush passed.
FIR09-00600 INSP-Supply line flush11/12/200911/13/200911/13/2009 2:00:24 PMAPASS
The underground flush passed.
BLD09-01685 FIRE-Final Inspection11/12/200911/13/200911/13/2009 1:04:55 PMAPASS
Life safety passed.
BLD09-00869 FIRE-Final Inspection11/13/200911/13/200911/13/2009 12:48:00 PMPPASS
Life safety passed.
FIR09-00628 INSP-Final Inspection11/12/200911/13/200911/13/2009 12:39:54 PMAPASS
Permit finaled.
BLD09-01982 FIRE-Final Inspection11/12/200911/13/200911/13/2009 12:30:44 PMAPASS
life safety passed
BLD09-01339 FIRE-Final Inspection11/12/200911/13/200911/13/2009 9:27:43 AMAPASS
Life safety passed.
FIR09-00640 INSP-Final Inspection11/12/200911/13/200911/13/2009 8:31:09 AMAPASS
permit finaled
BLD09-00869 FIRE-Final Inspection11/12/200911/13/200911/13/2009 7:29:03 AMAFAIL
The fire alarm db readings passed. All other items passed except the exit signs have been wired up to the light switches which is incorrect.