ESC07-01602
| Tracking Control | 11/13/2009 | 11/13/2009 | 11/13/2009 3:24:22 PM | P | CANC |
|
|
Duplicate.
|
ESC07-01602
| Tracking Control | 11/12/2009 | 11/13/2009 | 11/13/2009 3:24:12 PM | A | PART |
|
|
Verbal to RP: Prior to the end of the work day, install a sediment barrrier at the front of lot. Will re-inspect on 11/16/09PM.
|
ESC09-00678
| Site Preparation | 11/12/2009 | 11/13/2009 | 11/13/2009 3:22:54 PM | A | FAIL |
|
|
Verbal correction to RP: 1. Install a sediment barrier along the front of the stock pile. 2. clean up all sediment and debris off of all hard surfaces. 3. Prior to any concrete pours to provide a concrete wash out it that is lined. Will re-inspect on 11/16/09 AM.
|
ESC09-00713
| Site Preparation | 11/12/2009 | 11/13/2009 | 11/13/2009 2:03:04 PM | A | PASS |
|
|
|
ESC09-00713
| Site Preparation | 11/13/2009 | 11/13/2009 | 11/13/2009 2:02:45 PM | | PASS |
|
|
|
ESC09-00181
| Tracking Control | 11/12/2009 | 11/13/2009 | 11/13/2009 1:44:21 PM | P | PART |
|
|
Verbal to RP: Relocate ESC signs to the front of project where they are visable from the road.
|
ESC09-00187
| Tracking Control | 11/12/2009 | 11/13/2009 | 11/13/2009 1:44:10 PM | P | PART |
|
|
Verbal to RP: Relocate ESC signs to the front of project where they are visable from the road.
|
ESC09-00186
| Tracking Control | 11/12/2009 | 11/13/2009 | 11/13/2009 1:43:57 PM | P | PART |
|
|
Verbal to RP: Relocate ESC signs to the front of project where they are visable from the road.
|
ESC09-00184
| Tracking Control | 11/12/2009 | 11/13/2009 | 11/13/2009 1:43:48 PM | P | PART |
|
|
Verbal to RP: Relocate ESC signs to the front of project where they are visable from the road.
|
ESC09-00182
| Tracking Control | 11/12/2009 | 11/13/2009 | 11/13/2009 1:43:37 PM | P | PART |
|
|
Verbal to RP: Relocate ESC signs to the front of project where they are visable from the road.
|
ESC09-00721
| General Inspection | 11/13/2009 | 11/13/2009 | 11/13/2009 11:01:05 AM | P | PASS |
|
|
No issue of dewatering that were a concern from ACHD.
|
ESC09-00021
| BMP Violation | 11/13/2009 | 11/13/2009 | 11/13/2009 10:53:50 AM | A | PART |
|
|
Verbal to RP: Once plates are removed from the storm drain inlets, place in approved storm drain inlet protection.
|