FIR18-00464
| INSP-Sprinkler Rough-in | 11/9/2018 | 11/13/2018 | 11/13/2018 12:00:00 AM | A | PART |
|
|
Reviewed inspection comments made by Jim P. for area B. All of the comments seemed to be addressed correctly.
The area above each foyer is on hold until the hvac is installed. These areas are supposed to be supplied with heat. At a later date adequate heat shall be verified and or a heat sensor tied to the fire alarm panel may be required.
Area B Phone #: ###-#### >> Inspection requested via web by Matthew Lewis
|
FIR18-00848
| INSP-Sprinkler Rough-in | 11/9/2018 | 11/13/2018 | 11/13/2018 12:00:00 AM | A | PASS |
|
|
Underground piping ok to cover.
Jeremy-underground Phone #: ###-####
|
FIR18-00587
| INSP-Final Inspection | 11/12/2018 | 11/13/2018 | 11/13/2018 12:00:00 AM | A | FAIL |
|
|
- Could not ring bell.
- Sign on riser room door.
- Hanger on riser.
Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
FIR16-00563
| INSP-Final Inspection | 11/12/2018 | 11/13/2018 | 11/13/2018 12:00:00 AM | A | PASS |
|
|
Performed tamper and flow tests. All ok
Looked at basement. ok
Walked around spot checking sprinklers. ok
*** They need to add signs to the risers which will need to be coordinated with fire alarm.
*** They need to perform a forward flow test.
This is inspection for TCO at Phase 1 as directed by General Contractor. Please call Lonnie with Time frame. Will include tampers flows and dry system trip test to put all fire sprinkler systems in service. Phone #: ###-#### >> Inspection requested via web by Jeff Packham
|
FIR18-00311
| INSP-Sprinkler Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 12:00:00 AM | P | PASS |
|
|
Check three places of tenting the previous inspector was concerned about. All three places appeared to be ok.
Called went to voice mail. Left message 3:29
Tenting Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
|