Inspections for the day of: Friday, November 14, 2008.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC07-00904 General Inspection11/14/200811/14/200811/14/2008 2:27:50 PMPPASS
wENT OVER THE PROCESS OF DEWATERING WITH THE rp AND THE REQUIRMENT THAT ARE NEEDED
ESC08-00948 General Inspection11/14/200811/14/200811/14/2008 2:27:09 PMPCANC
ESC08-00948 Site Preparation11/14/200811/14/200811/14/2008 2:02:49 PM PART
told Aplicant that he needs to provide a RP for his project. Also to provide a lined concrete washout pit prior to the concrete pour date. Will re-inspect on 11/19/08.
ESC08-00734 Tracking Control11/12/200811/14/200811/14/2008 1:17:57 PMAPASS
All tracking has been cleaned up. Street washed occured.
ESC07-01487 General Inspection11/14/200811/14/200811/14/2008 12:54:28 PMPPASS
ESC08-00073 General Inspection11/14/200811/14/200811/14/2008 11:57:03 AMPFAIL
Spoke with RP over the pertaining issues.
Correction Notice:
Provide a concrete washout pit.
Clean up all stucco washout off the side of the hillside. Will re-inspect on 11/18/08
Failure to comply will result in a stop work order.
ESC08-00361 Tracking Control11/12/200811/14/200811/14/2008 10:43:54 AMAPASS
See previous inspection.
ESC08-00725 Site Preparation11/13/200811/14/200811/14/2008 10:11:43 AMAPASS
Actual work will not start until 11/17/08. Will re-inspect on 11/18/08.
ESC08-00819 Site Preparation11/14/200811/14/200811/14/2008 9:44:49 AM PASS
ESC07-01576 General Inspection11/14/200811/14/200811/14/2008 9:41:08 AMAFAIL
Left a message with RP.
Told RP to clean up concrete spoil pile located behind the porter pottie. Also to clean up any tracking that occurs today from the concrete pour. Also instructed the concrete trucks to clean out back at the batch plant. Will re-inspect on 11/17/08
ESC08-00183 General Inspection11/14/200811/14/200811/14/2008 8:44:09 AMAPASS
ESC08-00944 Site Preparation11/14/200811/14/200811/14/2008 8:38:13 AMAPART
Need to clean up sidewalks infront of lot.
ESC08-00912 Site Preparation11/14/200811/14/200811/14/2008 8:35:59 AMAFAIL
Need to clean of side walks from foot tracking and the gutterpan where there is concrete residule. Told RP to have it completed by 11/17/08 AM
ESC08-00464 Random Inspection11/14/200811/14/200811/14/2008 8:29:21 AMAPASS