Inspections for the day of: Wednesday, November 15, 2006.
Number of inspections: 25
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-02226 FIRE-Final Inspection11/14/200611/15/200611/15/2006 5:34:37 PMPPASS
Life safety finaled
BLD06-02225 FIRE-Final Inspection11/14/200611/15/200611/15/2006 5:34:02 PMPPASS
Life safety finaled
FIR06-00641 INSP-Sprinkler Rough-in/Hydro11/14/200611/15/200611/15/2006 5:32:51 PMPPASS
Underground hydro test passed.
FIR06-00740 INSP-Sprinkler Rough-in/Hydro11/15/200611/15/200611/15/2006 3:50:38 PMPPASS
Sprinkler piping is ok to cover
FIR06-00751 INSP-Final Inspection11/15/200611/15/200611/15/2006 3:14:39 PMPCANC
Grant will reschedule for tomorrow
BLD06-01581 FIRE-Final Inspection11/15/200611/15/200611/15/2006 3:14:06 PMPFAIL
The emergency light in the main lobby on the left hand wall as you walk in does not work. All other items are ok.
FIR06-00802 INSP-Final Inspection11/14/200611/15/200611/15/2006 2:41:07 PMAPASS
Permit finaled
FIR05-00582 INSP-Sprinkler Rough-in11/15/200611/15/200611/15/2006 2:06:44 PMPPASS
Pendant heads in the pharmacy area, as installed in the ceiling tile have passed. Waiting on alarms and life safety.
BLD06-01831 FIRE-Conference11/14/200611/15/200611/15/2006 1:52:12 PMPPASS
The contractor had a question about a pipe penatration through a rated wall
FIR06-00662 INSP-Sprinkler Rough-in/Hydro11/14/200611/15/200611/15/2006 1:33:08 PMAPASS
Underground flush passed.
BLD06-01566 FIRE-Final Inspection11/13/200611/15/200611/15/2006 1:32:42 PMACANC
Contractor will reschedule for friday.
FIR06-00498 INSP-Sprinkler Rough-in/Hydro11/14/200611/15/200611/15/2006 1:11:52 PMAPASS
Underground hydro test passed. The end of the test was witnessed by Mike Clay the general contractors representative.
FIR06-00500 INSP-Sprinkler Rough-in/Hydro11/14/200611/15/200611/15/2006 1:11:29 PMAPASS
Underground hydro test passed. The end of the test was witnessed by Mike Clay the general contractors representative.
BLD06-01779 FIRE-Final Inspection11/14/200611/15/200611/15/2006 12:00:17 PMAFAIL
Provide indicator at the main exit and either remove the non required exit discharge lights or provide listed devices for the damp and cold temperatures.
BLD06-02380 FIRE-Final Inspection11/14/200611/15/200611/15/2006 11:57:59 AMPCANC
To be rescheduled for tomorrow
FIR06-00826 INSP-Final Inspection11/14/200611/15/200611/15/2006 11:57:43 AMPCANC
To be rescheduled for tomorrow
BLD06-02487 FIRE-Final Inspection11/14/200611/15/200611/15/2006 11:48:33 AMAPASS
Life safety finaled
FIR06-00808 INSP-Final Inspection11/15/200611/15/200611/15/2006 11:48:15 AMPPASS
permit finaled
FIR06-00320 INSP-Final Inspection11/13/200611/15/200611/15/2006 11:16:56 AMAFAIL
Contractor was not ready for flush. The only items I inspected was the sprinkler heads. The head in the utility room is blocked by the light fixture. Many heads have been added. I told brian that he needs to provide as-builts to the returning inspector
FIR06-00817 INSP-Final Inspection11/9/200611/15/200611/15/2006 9:38:59 AMAPASS
permit finaled
BLD06-02364 FIRE-Final Inspection11/14/200611/15/200611/15/2006 9:37:43 AMAPASS
life safety finaled
FIR06-00612 INSP-Alarm Testing11/14/200611/15/200611/15/2006 9:37:27 AMAPASS
permit finaled
FIR06-00309 INSP-Final Inspection11/9/200611/15/200611/15/2006 9:36:07 AMAFAIL
Missing the 30cd a/v in the storage room as shown on the revision 2 plans.
BLD06-01120 FIRE-Final Inspection11/9/200611/15/200611/15/2006 9:35:33 AMAFAIL
No life safety performed since the fire alarm failed
FIR06-00738 INSP-Final Inspection11/14/200611/15/200611/14/2006 2:01:34 PMAFAIL
A retaining strap is needed on the sidebeam bracket in the wormens sauna and the hanger in the mens sauna needs to be taken to the structure and provided with a retaining strap.