Inspections for the day of: Tuesday, November 15, 2016.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-04076 FIRE-Final Inspection11/15/201611/15/201611/15/2016 2:28:01 PMPPASS
life safety passed.
FIR16-00336 INSP-Sprinkler Rough-in11/15/201611/15/201611/15/2016 2:26:51 PMPFAIL
I pointed out several locations where tenting needed modified which included in the Master Bedroom and a vertical piece of pipe on the second floor above the Master Bedroom. Also a letter is needed that states the spray on foam insulation is compatible with the cpvc piping. I noted that the spray on foam has been sprayed behind as well as on top fo the piping. The building contractor, Bob, stated that there is adequate insulation behind the piping and the foam on the interior side of the piping is not detrimental to heat transfer. Another cover inspection is needed with the above corrections prior to covering the piping.
NAF16-00057 INSP-Sprinkler Rough-in/Hydro11/14/201611/15/201611/15/2016 12:04:44 PMAFAIL
Overhead hydro tests failed due to visible leak on the ground and pressure loss at the guages. I also noted that the supply piping to the FDC needs hydro tested.
FIR16-00677 INSP-Sprinkler Rough-in11/14/201611/15/201611/15/2016 9:41:02 AMAFAIL