FIR06-00639
| INSP-Sprinkler Rough-in | 11/16/2006 | 11/16/2006 | 11/17/2006 5:17:18 PM | P | PART |
|
|
Need to provide correct as-builts reflecting actual installation of overhead piping for the 3rd floor previous to approval for cover.
|
FIR06-00680
| INSP-Alarm Testing | 11/13/2006 | 11/16/2006 | 11/16/2006 3:47:47 PM | A | PASS |
|
|
Fire alarm work passed final inspection.
|
FIR06-00320
| INSP-Final Inspection | 11/16/2006 | 11/16/2006 | 11/16/2006 3:46:43 PM | P | PART |
|
|
UG flush completed, need to install missing head in the basement hall, calc. stickers, lock control valves open, provide annual inspection tag.
|
FIR05-00425
| INSP-Sprinkler Rough-in | 11/15/2006 | 11/16/2006 | 11/16/2006 12:50:51 PM | A | PART |
|
|
Retest of the OH hydrostatic for the 6th floor passed inspeciton.
|
BLD06-02391
| FIRE-Final Inspection | 11/15/2006 | 11/16/2006 | 11/16/2006 11:33:54 AM | A | PASS |
|
|
Life safety is satisfactory, inspection passed.
|
BLD06-00501
| FIRE-Final Inspection | 11/15/2006 | 11/16/2006 | 11/16/2006 11:32:40 AM | A | PASS |
|
|
Life safety inspection passed, per contractor signage at the fire lane curbs to be completed pending rain delay.
|
FIR06-00534
| INSP-Sprinkler Rough-in/Hydro | 11/13/2006 | 11/16/2006 | 11/16/2006 10:51:30 AM | A | FAIL |
|
|
Pendent head in office 305 is overspaced off an adjacent wall, head in the mechanical closet is partially blocked and installed too close to adjacent ductwork.
|
FIR06-00826
| INSP-Final Inspection | 11/15/2006 | 11/16/2006 | 11/16/2006 10:46:36 AM | A | NR |
|
|
Per contractor, project inspection pending interconnection of the access controlled egress door to the fire alarm system.
|
BLD06-01581
| FIRE-Final Inspection | 11/15/2006 | 11/16/2006 | 11/16/2006 9:47:23 AM | A | PASS |
|
|
c/n item has been completed, fire life safety passed final inspection.
|