Inspections for the day of: Thursday, November 16, 2006.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-02329 FIRE-Final Inspection11/15/200611/16/200611/17/2006 11:32:44 AMAPASS
Life safety finaled. Doors have been corrected.
BLD05-02328 FIRE-Final Inspection11/15/200611/16/200611/17/2006 11:32:20 AMAPASS
Life safety finaled. Doors have been corrected.
BLD05-01690 FIRE-Final Inspection11/16/200611/16/200611/16/2006 8:06:33 PMPPASS
Life safety finaled
FIR06-00468 INSP-Final Inspection11/16/200611/16/200611/16/2006 3:44:05 PMPFAIL
Still need to address the different sprinkler heads. K factors are different and the anti-freeze solution needs to be verified.
BLD06-01672 FIRE-Final Inspection11/15/200611/16/200611/16/2006 12:55:06 PMPCANC
to be rescheduled
FIR06-00866 INSP-Final Inspection11/16/200611/16/200611/16/2006 12:54:26 PMPFAIL
existing insulation is hanging down and blocking coverage. All other items are ok
BLD06-03007 FIRE-Final Inspection11/16/200611/16/200611/16/2006 11:21:10 AMPPART
A temporary occupancy was given with dave hannimans permission until the new door and related hardware are installed. Need to remove or repair the exit signs and tag the extinguisher.
BLD05-03026 FIRE-Final Inspection11/15/200611/16/200611/16/2006 10:44:37 AMPPASS
Life safety finaled
BLD05-02880 FIRE-Conference11/15/200611/16/200611/16/2006 9:52:56 AMAPASS
The owners representative wanted me to ok their new layout to meet the sprinkler analasis. They are reinstalling the racks starting in the northwest corner. They are providing 6" transverse and longitudinal flu spaces with 48" isles. This meets the intent of the letter and if carried out will be approved by me.