FIR09-00384
| INSP-Sprinkler Rough-in | 11/16/2009 | 11/16/2009 | 11/16/2009 6:15:09 PM | P | PART |
|
|
Overhead work approved for cover at the sheetrock ceilings throughout.
|
FIR09-00347
| INSP-Final Inspection | 11/16/2009 | 11/16/2009 | 11/16/2009 6:14:07 PM | P | PART |
|
|
Final pending forward flow and main drain tests when riser is finished.
|
BLD09-01337
| FIRE-Final Inspection | 11/16/2009 | 11/16/2009 | 11/16/2009 6:13:15 PM | P | NR |
|
|
Items noted include two fire extinguishers at the 2nd floor common corridor overdue current annual certification, remove dust cover at the smoke detector, replace drop ceiling tiles to maintain thermal response for the pendent sprinklers, clear path of egress where obstructed at the first floor corridors.
|
BLD04-02761
| FIRE-Conference | 11/16/2009 | 11/16/2009 | 11/16/2009 6:07:55 PM | P | DONE |
|
|
Regarding project inspection schedule.
|
FIR09-00550
| INSP-Final Inspection | 11/16/2009 | 11/16/2009 | 11/16/2009 6:06:35 PM | P | NH |
|
|
No access to complete inspection, rescheduled as discussed.
|
FIR09-00257
| INSP-Sprinkler Rough-in | 11/13/2009 | 11/16/2009 | 11/16/2009 1:25:00 PM | A | PART |
|
|
Plan modification for changes at unit 519 to exposed steel piping and pendent heads verified for field compliance, overhead cover okayed at unit 520, need to provide sheetrock ceilings and adequate freeze protection prior to permit final.
|
FIR09-00614
| INSP-Final Inspection | 11/12/2009 | 11/16/2009 | 11/16/2009 12:52:09 PM | A | PASS |
|
|
Scope of fire alarm work passed field testing, incorrect descriptor at the fire sprinkler riser dry system main control valve corrected by contractor while on site, permit final approved.
|
FIR09-00580
| INSP-Conference | 11/16/2009 | 11/16/2009 | 11/16/2009 12:49:25 PM | A | DONE |
|
|
Regarding site inspection protocol.
|
BLD09-01635
| FIRE-Final Inspection | 11/13/2009 | 11/16/2009 | 11/16/2009 12:46:10 PM | A | PASS |
|
|
Fire life safety completed acceptable, inspection passed.
|