NAF15-00035
| INSP-Sprinkler Rough-in | 11/13/2015 | 11/16/2015 | 11/16/2015 4:32:30 PM | P | PART |
|
|
Delay in hot taping at street water main connection prevented full underground inspection from happening. Water company on site at time of inspection. Mechanical tee at tap inspected, OK to cover.
|
NAF14-00023
| INSP-Final | 11/16/2015 | 11/16/2015 | 11/16/2015 4:30:22 PM | P | PASS |
|
|
Flow test of unit 3596 completed satisfactory. Modifications by contractor were performed on sight to flow switch to achieve successful test. Scope of work complete, permit finaled.
|
NAF15-00025
| INSP-Sprinkler Rough-in | 11/16/2015 | 11/16/2015 | 11/16/2015 2:17:32 PM | P | DONE |
|
|
Early Start Inspection on 11/3 for riser stub in. Riser ok to pour floor slab, discussed pouring around a ring for seismic protection. Verified appropriate depth on stub outside of building footing. End of pipe submerged in dirt, unsure if capped, ensure flush is done well at later date.
Initially posted to NAF15-00025 which is alarm permit. Added here to ensure documented appropriately.
|