Inspections for the day of: Monday, November 16, 2015.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-01444 Site Preparation11/16/201511/16/201511/16/2015 5:01:12 PMPPASS
Mark// please call before Phone #: ###-####
ESC14-01059 Aging Inspection11/16/201511/16/201511/16/2015 4:33:47 PM PASS
WIP. Materials and washout are contained on site. No discharges or trackout from site. No issues.
ESC14-00488 General Inspection11/16/201511/16/201511/16/2015 3:51:44 PM PASS
ESC14-00296 General Inspection11/16/201511/16/201511/16/2015 3:28:30 PM PASS
Site entrances and perimeter are stabilized. Vertical construction in progress. No trackout to streets, no discharges observed. No corrections at this time.
ESC14-01063 General Inspection11/16/201511/16/201511/16/2015 2:37:26 PM PASS
SFHs in progress on Bent Bow in Eyrie Canyon #8. Permit signs posted, trash contained, and no trackout or discharges observed.

Hillside seeding and revegetation around culdesac is established and no erosion rills or gullies observed on cut hillsides. Recnently installed water line connection behind home on Bent Bow will need to be stabilized. BMPs down slope are installed to contain sediment.

Active construction/grading is occuring in EC #9, and no issues were observed. Approved.
ESC15-00031 General Inspection11/16/201511/16/201511/16/2015 1:58:13 PM PASS
WIP on SFHs in Fairmont Square. Permanent stormwater controls and subdivision landscaping are complete. No erosion issues observed of drainage failures.

Home builders are keeping off open lots, no major trackout or loose sediment. Trash containment is provided. No spills or discharges observed. Approved.
ESC13-01279 General Inspection11/16/201511/16/201511/16/2015 1:42:22 PM CANC
rescheduled for 11/17
ESC15-00939 Site Final11/16/201511/16/201511/16/2015 12:56:56 PMAPASS
Home construction on exterior complete and yard has been stabilized. ESC permit conditions satisifed.
ESC14-00940 DOC - Permit Finaled11/16/201511/16/201511/16/2015 12:52:39 PMPPASS
ESC14-00940 Aging Inspection11/16/201511/16/201511/16/2015 12:46:33 PM PASS
Work on going on detached garage behind home. Frame is up and earthwork/foundation is complete and driveway to gargage is paved. No further ESC inspections necessary. ESC permit finaled
ESC14-01097 General Inspection11/16/201511/16/201511/16/2015 12:29:35 PM PASS
WIP. Framing on warehouse structure has resumed. No trackout or discharges from site. Stabilized construction entrance and worker parking area is in good condition.

Approved.
ESC15-00089 Aging Inspection11/16/201511/16/201511/16/2015 12:10:53 PM PASS
CBH project in Dunham Commons is complete, landscaped, and occupied. Active projects in subdivision by CBH are in compliance and temporary BMPs are installed and being utilized. Permit finaled.
ESC15-00089 DOC - Permit Finaled11/16/201511/16/201511/16/2015 12:09:48 PMPPASS
ESC14-01053 Aging Inspection11/16/201511/16/201511/16/2015 11:55:04 AM PASS
Home complete, occupied, and landscaped in front yard. Both adajecent lots are occupied/stabilized and backyard is being worked on by homeowner.

Permit conditions satisfied.
ESC14-01053 DOC - Permit Finaled11/16/201511/16/201511/16/2015 11:53:53 AMPPASS
ESC15-01484 Site Preparation11/13/201511/16/201511/16/2015 11:33:22 AMAFAIL
Dan Clark - ###-####

GC - RP license is expired, used invalid RP during application process

-post Yellow permit sign
- complete RP recertification
- warn subcontractors about driving on open parcel (has not yet occured)
- provide trash container for workers
- provide concrete

Will check back for corrections later this week
ESC14-01052 General Inspection11/16/201511/16/201511/16/2015 11:00:59 AM PART
RP Pat Palmer onsite. All 4-plex units are underway and have individual trash containers. Lined concrete washout box has been utilized.

Over weekend the parking lot and access drive were swept and clean in response to Correction Request by Mike Jordan. Sweeping was thorough and no trackout or sediment runoff is occuring at site.

Correction:
- Need to pick up litter and consruction material wrappings that are trapped along north canal/ditch bank and make sure light weight trash is either covered or weighed down to prevent being blown by wind.
ESC15-00063 Aging Inspection11/16/201511/16/201511/16/2015 9:53:14 AM PASS
Project complete. No sediment leaving site. No further construction or materials on site. Permit finaled; BLD still open.
ESC15-00063 DOC - Permit Finaled11/16/201511/16/201511/16/2015 9:52:33 AMPPASS
ESC14-00328 General Inspection11/16/201511/16/201511/16/2015 9:10:51 AM PASS
Spoke with Wetlands Group' Shane Hopkins regarding project. Tree replanting and minor grading activity is complete. Stockpile of soil at edge of Willow Lane parking lot will be utilized and maintained by Boise Parks and Recreation under their Annual ESC permit ( ESC15-00590 valid May 2015 - 2016) No sediment runoff or storage of construction materials is occuring at site, stockpile has perimeter sediment control.
ESC14-00328 DOC - Permit Finaled11/16/201511/16/201511/16/2015 9:06:38 AMPPASS
ESC14-00462 General Inspection11/16/201511/16/201511/16/2015 8:50:05 AM PASS