ESC15-01444
| Site Preparation | 11/16/2015 | 11/16/2015 | 11/16/2015 5:01:12 PM | P | PASS |
|
|
Mark// please call before Phone #: ###-####
|
ESC14-01059
| Aging Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 4:33:47 PM | | PASS |
|
|
WIP. Materials and washout are contained on site. No discharges or trackout from site. No issues.
|
ESC14-00488
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 3:51:44 PM | | PASS |
|
|
|
ESC14-00296
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 3:28:30 PM | | PASS |
|
|
Site entrances and perimeter are stabilized. Vertical construction in progress. No trackout to streets, no discharges observed. No corrections at this time.
|
ESC14-01063
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 2:37:26 PM | | PASS |
|
|
SFHs in progress on Bent Bow in Eyrie Canyon #8. Permit signs posted, trash contained, and no trackout or discharges observed.
Hillside seeding and revegetation around culdesac is established and no erosion rills or gullies observed on cut hillsides. Recnently installed water line connection behind home on Bent Bow will need to be stabilized. BMPs down slope are installed to contain sediment.
Active construction/grading is occuring in EC #9, and no issues were observed. Approved.
|
ESC15-00031
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 1:58:13 PM | | PASS |
|
|
WIP on SFHs in Fairmont Square. Permanent stormwater controls and subdivision landscaping are complete. No erosion issues observed of drainage failures.
Home builders are keeping off open lots, no major trackout or loose sediment. Trash containment is provided. No spills or discharges observed. Approved.
|
ESC13-01279
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 1:42:22 PM | | CANC |
|
|
rescheduled for 11/17
|
ESC15-00939
| Site Final | 11/16/2015 | 11/16/2015 | 11/16/2015 12:56:56 PM | A | PASS |
|
|
Home construction on exterior complete and yard has been stabilized. ESC permit conditions satisifed.
|
ESC14-00940
| DOC - Permit Finaled | 11/16/2015 | 11/16/2015 | 11/16/2015 12:52:39 PM | P | PASS |
|
|
|
ESC14-00940
| Aging Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 12:46:33 PM | | PASS |
|
|
Work on going on detached garage behind home. Frame is up and earthwork/foundation is complete and driveway to gargage is paved. No further ESC inspections necessary. ESC permit finaled
|
ESC14-01097
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 12:29:35 PM | | PASS |
|
|
WIP. Framing on warehouse structure has resumed. No trackout or discharges from site. Stabilized construction entrance and worker parking area is in good condition.
Approved.
|
ESC15-00089
| Aging Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 12:10:53 PM | | PASS |
|
|
CBH project in Dunham Commons is complete, landscaped, and occupied. Active projects in subdivision by CBH are in compliance and temporary BMPs are installed and being utilized. Permit finaled.
|
ESC15-00089
| DOC - Permit Finaled | 11/16/2015 | 11/16/2015 | 11/16/2015 12:09:48 PM | P | PASS |
|
|
|
ESC14-01053
| Aging Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 11:55:04 AM | | PASS |
|
|
Home complete, occupied, and landscaped in front yard. Both adajecent lots are occupied/stabilized and backyard is being worked on by homeowner.
Permit conditions satisfied.
|
ESC14-01053
| DOC - Permit Finaled | 11/16/2015 | 11/16/2015 | 11/16/2015 11:53:53 AM | P | PASS |
|
|
|
ESC15-01484
| Site Preparation | 11/13/2015 | 11/16/2015 | 11/16/2015 11:33:22 AM | A | FAIL |
|
|
Dan Clark - ###-####
GC - RP license is expired, used invalid RP during application process
-post Yellow permit sign - complete RP recertification - warn subcontractors about driving on open parcel (has not yet occured) - provide trash container for workers - provide concrete
Will check back for corrections later this week
|
ESC14-01052
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 11:00:59 AM | | PART |
|
|
RP Pat Palmer onsite. All 4-plex units are underway and have individual trash containers. Lined concrete washout box has been utilized.
Over weekend the parking lot and access drive were swept and clean in response to Correction Request by Mike Jordan. Sweeping was thorough and no trackout or sediment runoff is occuring at site.
Correction: - Need to pick up litter and consruction material wrappings that are trapped along north canal/ditch bank and make sure light weight trash is either covered or weighed down to prevent being blown by wind.
|
ESC15-00063
| Aging Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 9:53:14 AM | | PASS |
|
|
Project complete. No sediment leaving site. No further construction or materials on site. Permit finaled; BLD still open.
|
ESC15-00063
| DOC - Permit Finaled | 11/16/2015 | 11/16/2015 | 11/16/2015 9:52:33 AM | P | PASS |
|
|
|
ESC14-00328
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 9:10:51 AM | | PASS |
|
|
Spoke with Wetlands Group' Shane Hopkins regarding project. Tree replanting and minor grading activity is complete. Stockpile of soil at edge of Willow Lane parking lot will be utilized and maintained by Boise Parks and Recreation under their Annual ESC permit ( ESC15-00590 valid May 2015 - 2016) No sediment runoff or storage of construction materials is occuring at site, stockpile has perimeter sediment control.
|
ESC14-00328
| DOC - Permit Finaled | 11/16/2015 | 11/16/2015 | 11/16/2015 9:06:38 AM | P | PASS |
|
|
|
ESC14-00462
| General Inspection | 11/16/2015 | 11/16/2015 | 11/16/2015 8:50:05 AM | | PASS |
|
|
|