PLM95-01369
| INSP - Framing/ Rough-in | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | | PASS |
|
|
/ / 330 - r/i ok
|
PLM95-01513
| INSP - Sewer and Water lines | 11/16/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | A | PASS |
|
|
11/16/95 330 - done it last night
|
PLM95-01711
| INSP - Ground work | 11/16/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | A | PASS |
|
|
11/16/95 330 -
|
PLM95-01730
| INSP - Plumbing Rough-in | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | P | PASS |
|
|
11/17/95 330 - 2 W/C 2 LAV 2 SH/TUB 1 SINK 1 W/H 1 W/B
|
PLM95-01731
| INSP - Sprinkler & Backflow | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | P | PASS |
|
|
11/17/95 330 -
|
PLM95-01733
| INSP - Plumbing Rough-in | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | P | PASS |
|
|
11/17/95 330 - INSTALL EMERGENCY SHOWER AND EYEWASH FLOOR DRAINS TRENCH ASKED FOR AN INSPECTION BUT NOT WHAT KIND SO I THOUGHT (OH NO) IT WAS A inspection were do
|
PLM95-01738
| INSP - Plumbing Rough-in | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | P | PASS |
|
|
11/17/95 330 - 10 FIXTURES 2-wc,3-lav,1-tub,1-sh,1-si,1-wb,1-wh
|
PLM95-01689
| INSP - Plumbing Rough-in | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | P | PASS |
|
|
11/17/95 330 -
|
PLM95-00827
| INSP - Final | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | P | PASS |
|
|
11/17/95 330 - 2-wc,3-lav,1-tub,1-sh,1-si,1-wb,1-wh
|
PLM95-01203
| INSP - Final | 11/17/1995 | 11/17/1995 | 11/17/1995 12:00:00 AM | P | PASS |
|
|
11/17/95 330 - 2-wc,3-lav,1-tub,1-sh,2-si,1-wb,1-wh
|