Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-00795 BLD-Framing/Rough-in11/16/199911/17/199911/17/1999 12:00:00 AMAPART
GARY ###-#### FR INSP Walk thru, framing.
BLD99-02556 BLD-Final11/16/199911/17/199911/17/1999 12:00:00 AMAPASS
KEY OVER SIDE GAR DOOR --JOHN ###-#### FN OCC
BLD99-02691 BLD-Framing/Rough-in11/16/199911/17/199911/17/1999 12:00:00 AMACANC
STEVE-- ###-#### RE-INSP FR
BLD99-02364 BLD-Energy code compliance11/16/199911/17/199911/17/1999 12:00:00 AMAPASS
JAY ###-#### ENERGY CODE
BLD99-02364 BLD-Framing/Rough-in11/16/199911/17/199911/17/1999 12:00:00 AMAPASS
JAY ###-#### FR INSP
BLD99-01994 BLD-Final11/17/199911/17/199911/17/1999 12:00:00 AMPNR
Scheduled by a contractor via Hello! on 11/17/1999 at 08:15:30. Contact: . Needs electrical approved.
BLD99-02670 BLD-Other11/17/199911/17/199911/17/1999 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 11/17/1999 at 08:16:35. Contact: .
BLD99-03008 BLD-Framing/Rough-in11/17/199911/17/199911/17/1999 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 11/17/1999 at 08:22:32. Contact: ###-####. Holes drilled in trussed, need engineer to ok, other wise ok to cover. Re-inspection required.
BLD98-02368 BLD-Framing/Rough-in11/17/199911/17/199911/17/1999 12:00:00 AMPPART
RE-INSP FR--- IRAN-- ###-####-CALL 1ST BEFORE INSP Fireblocking and insulation inspection reqd. Engineer approved roof & stairs at entry.
BLD99-02081 BLD-Final11/17/199911/17/199911/17/1999 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 11/17/1999 at 10:45:31. Contact: ###-####.
BLD99-02374 BLD-Framing/Rough-in11/17/199911/17/199911/17/1999 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 11/17/1999 at 10:46:51. Contact: ###-####.
MEC99-03872 Rough-in11/17/199911/17/199911/17/1999 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 11/17/1999 at 11:05:05. Contact: ###-####.
MEC99-03866 Rough-in11/17/199911/17/199911/17/1999 12:00:00 AMPPASS
RE-INSP FIREPLACE-- STEVE ###-#### CELL
BLD99-01927 BLD-Framing/Rough-in11/17/199911/17/199911/17/1999 12:00:00 AMPPART
STEVE ###-#### RE-INSP FR Ok to rock still has corrections which are posted on site.
MEC99-03140 Final11/17/199911/17/199911/17/1999 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 11/17/1999 at 11:19:53. Contact: ###-####.