FIR05-00571
| INSP-Sprinkler Rough-in | 11/16/2005 | 11/17/2005 | 11/18/2005 4:11:46 PM | A | PART |
|
|
Sprinkler piping is ok to cover except in the areas where deficiencies have been noted on the city approve plans. Resubmittals of the hydraulic calcs for area #3 are needed since upright heads exceed the 120 maz spacing allowed.
|
BLD05-01373
| FIRE-Final Inspection | 11/16/2005 | 11/17/2005 | 11/17/2005 2:50:33 PM | P | PASS |
|
|
fire life safety finaled
|
BLD05-01455
| FIRE-Final Inspection | 11/16/2005 | 11/17/2005 | 11/17/2005 2:08:15 PM | P | PASS |
|
|
Fire life safety finaled
|
FIR05-00523
| INSP-Final Inspection | 11/16/2005 | 11/17/2005 | 11/17/2005 2:07:50 PM | P | PASS |
|
|
Fire sprinkler finaled
|
BLD05-02852
| FIRE-Final Inspection | 11/15/2005 | 11/17/2005 | 11/17/2005 1:56:34 PM | A | FAIL |
|
|
hilary; Phone #: ###-#### Provide verification that the overhead sprinkler system is adequate for the racks and commodities installed per the fire dept racking review comments. Provide height limit signs for the maximum storage height.
|
FIR05-00739
| INSP-Sprinkler Rough-in/Hydro | 11/17/2005 | 11/17/2005 | 11/17/2005 11:22:31 AM | P | PART |
|
|
First floor hydro test and rough-in passed.
|