Inspections for the day of: Friday, November 17, 2006.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-00658 FIRE-Final Inspection11/16/200611/17/200611/17/2006 4:14:02 PMPFAIL
No city approved plans on site. No inspection performed.
FIR06-00543 INSP-Supply line flush11/17/200611/17/200611/17/2006 4:13:15 PMPPASS
Underground supply line flush passed.
MIS06-00243 FIR-Final11/17/200611/17/200611/17/2006 4:09:25 PMPFAIL
Ceiling tile has been installed but the door hardware on both doors has not been corrected.
FIR06-00836 INSP-Final Inspection11/16/200611/17/200611/17/2006 4:08:37 PMAPASS
Permit finaled. Sprinkler pendant in restroom was damaged and had to be changed out.
BLD06-03005 FIRE-Final Inspection11/17/200611/17/200611/17/2006 2:23:06 PMPPART
A temporary occupancy was given with dave hannimans permission until the single emergency light in the bar area has been repaired.
FIR06-00548 INSP-Sprinkler Rough-in/Hydro11/17/200611/17/200611/17/2006 2:08:04 PMPPASS
See city approved plans for hardlid areas marked with an "OK" that the sprinkler piping is ok to cover.
BLD06-01672 FIRE-Final Inspection11/16/200611/17/200611/17/2006 1:01:50 PMAPASS
Life safety finaled
FIR06-00684 INSP-Final Inspection11/16/200611/17/200611/17/2006 1:01:35 PMAPASS
permit finaled
BLD06-02108 FIRE-Conference11/16/200611/17/200611/17/2006 12:20:32 PMAPASS
Went over maximum occupant load signs and their location with the general contractor.
FIR06-00873 INSP-Final Inspection11/16/200611/17/200611/17/2006 11:15:54 AMAPASS
permit finaled
FIR06-00785 INSP-Final Inspection11/16/200611/17/200611/17/2006 10:40:25 AMAFAIL
Need to verify previous signals sent and test the dry system low air and wet system flow which did not operate
FIR06-00543 INSP-Sprinkler Rough-in/Hydro11/17/200611/17/200611/17/2006 9:15:08 AMAPASS
Meter proving room sprinkler piping is ok to cover
BLD06-00008 FIRE-Final Inspection11/16/200611/17/200611/17/2006 9:01:54 AMAPASS
Life safety finaled. Stickers at the main doors to be corrected.
FIR06-00463 INSP-Final Inspection11/15/200611/17/200611/17/2006 9:00:53 AMAPASS
Permit finaled. Forward flush passed.
FIR05-00644 INSP-Conference11/16/200611/17/200611/17/2006 8:29:42 AMAPASS
The conference was for the eaves. The eaves will have blown-in insulation and cardboard has been utilized to provide the necessary eave ventilation. Appears acceptable.