ELE09-02223
| Permanent Service | 11/17/2009 | 11/17/2009 | 11/17/2009 4:33:06 PM | P | PASS |
|
|
call prior to going Phone #: ###-#### Internet Inspection Request from: Neil Rumsey p/s u/g n ok, no esc this project
|
ELE09-02224
| Permanent Service | 11/17/2009 | 11/17/2009 | 11/17/2009 4:31:49 PM | P | PASS |
|
|
call prior going Phone #: ###-#### Internet Inspection Request from: Neil Rumsey p/s u/g rec ok, no esc this project
|
ELE09-02231
| Electrical Rough-In | 11/17/2009 | 11/17/2009 | 11/17/2009 4:05:39 PM | P | PART |
|
|
Phone #: ###-#### Internet Inspection Request from: Bob Glenn called contractor, ok to foam, need to move boxes in re-framed wall, find tub listing, nailplate low voltage wiring, will call for aqm inspectiion
|
ESC06-01782
| General Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 3:32:33 PM | P | PASS |
|
|
looked ok
|
ELE08-01021
| Final | 11/17/2009 | 11/17/2009 | 11/17/2009 3:31:39 PM | P | PASS |
|
|
ok to final
|
ELE08-01021
| ELE-Aging Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 3:31:09 PM | P | DONE |
|
|
please final or expire please,, Thanks,, #415 Tony Young see final
|
ESC09-00600
| General Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 2:58:31 PM | P | PASS |
|
|
looked ok at top
|
ESC09-00359
| General Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 2:57:23 PM | P | PASS |
|
|
looked ok
|
ESC09-00517
| General Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 2:56:41 PM | P | PASS |
|
|
|
ESC09-00392
| General Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 2:02:51 PM | P | PASS |
|
|
looked ok
|
ELE09-02243
| Electrical Rough-In | 11/17/2009 | 11/17/2009 | 11/17/2009 2:01:53 PM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Stuart Welton ric ok, no esc this project
|
ELE09-02243
| Final | 11/17/2009 | 11/17/2009 | 11/17/2009 2:01:32 PM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Stuart Welton ok to final, no esc this project
|
ELE09-02241
| Electrical Rough-In | 11/16/2009 | 11/17/2009 | 11/17/2009 1:36:34 PM | P | PART |
|
|
Pool bonding & Underground thanks Phone #: ###-#### Internet Inspection Request from: Lynn Cable called, pool bonding only ok, need to see horizon for u/g and rest installed before cover
|
ELE09-01596
| Electrical Rough-In | 11/16/2009 | 11/17/2009 | 11/17/2009 12:45:00 PM | P | PASS |
|
|
Potting compound inspection for light niche thanks Phone #: ###-#### Internet Inspection Request from: Lynn Cable pool light potting only ok
|
ELE09-02162
| Final | 11/16/2009 | 11/17/2009 | 11/17/2009 10:54:23 AM | A | PASS |
|
|
Please contact home owner to make sure she is home before you head up there ###-#### thank you Internet Inspection Request from: Tyler Bowen corrections made, ok to final, no esc this project
|
ELE09-02070
| Electrical Rough-In | 11/16/2009 | 11/17/2009 | 11/17/2009 9:50:31 AM | A | FAIL |
|
|
Justin-Floor Heat inspection please Phone #: ###-#### called contractor, told that tile guy covered floor heat with quickset, left correction notice, BCC shall not cover electrical wiring before inspection, left do not cover red tag
|
ELE09-01603
| Final | 11/16/2009 | 11/17/2009 | 11/17/2009 9:15:57 AM | A | PASS |
|
|
Please call Heath@###-#### prior to arrival to arrange access. Phone #: ###-#### Internet Inspection Request from: Joe Thomas ok to final, no esc this project
|
ELE09-01512
| Final | 11/16/2009 | 11/17/2009 | 11/17/2009 8:28:01 AM | A | PASS |
|
|
steve Phone #: ###-#### ok to final, no card to sign
|