BLD11-01572
| FIRE-Conference | 11/17/2011 | 11/17/2011 | 11/17/2011 4:01:33 PM | P | DONE |
|
|
Regarding modifications to the existing fire sprinkler system due to remodel work. Noted overspaced coverage at the new reception room 2nd floor.
|
FIR11-00534
| INSP-Sprinkler Rough-in/Hydro | 11/16/2011 | 11/17/2011 | 11/17/2011 3:54:56 PM | P | PASS |
|
|
UG fire supply line hydrostatic testing completed.
|
BLD11-02228
| FIRE-Final Inspection | 11/16/2011 | 11/17/2011 | 11/17/2011 3:43:32 PM | P | PASS |
|
|
Fire life safety inspection completed satisfactory.
|
BLD11-01591
| BLD-Final | 11/17/2011 | 11/17/2011 | 11/17/2011 3:30:28 PM | A | PASS |
|
|
Fire life safety finaled.
|
BLD11-01562
| BLD-Final | 11/17/2011 | 11/17/2011 | 11/17/2011 3:26:16 PM | A | PASS |
|
|
Fire life safety final approved.
|
BLD11-02688
| FIRE-Final Inspection | 11/16/2011 | 11/17/2011 | 11/17/2011 2:21:59 PM | A | PASS |
|
|
Life safety finaled.
|
BLD11-02163
| FIRE-Final Inspection | 11/16/2011 | 11/17/2011 | 11/17/2011 2:05:48 PM | A | FAIL |
|
|
Correction items incude; missing signage at the main entry/exit, post one fire extinguisher with current tag as discussed, provide approved hardware at one restroom, remove one non-required exit sign at the mercantile area or provide approved door hardware, building address numbers to meet IFC 2009 sec. 505.1.
|
FIR11-00530
| INSP-Final Inspection | 11/16/2011 | 11/17/2011 | 11/17/2011 1:43:40 PM | A | PASS |
|
|
Scope of fire alarm work passed inspection. Permit finaled.
|