PLM16-01584
| PLM-Aging Inspection | 11/17/2016 | 11/17/2016 | 11/22/2016 2:51:03 PM | | PEND |
|
|
|
PLM16-04096
| Plumbing Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 4:44:05 PM | P | PASS |
|
|
18855-NEW RESIDENTIAL PLUMBING INSTALLATION Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
|
PLM16-03071
| Final | 11/17/2016 | 11/17/2016 | 11/17/2016 4:28:18 PM | P | PART |
|
|
Contact for lock box and alarm code. Phone #: ###-#### Inspection requested via web by Todd Walter. Need to install backflow prevention at the plaster grinder.
|
PLM16-04180
| Final | 11/16/2016 | 11/17/2016 | 11/17/2016 4:27:11 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette
|
PLM16-04008
| Sprinkler (Final) | 11/17/2016 | 11/17/2016 | 11/17/2016 3:05:26 PM | P | PASS |
|
|
Robert Phone #: ###-####
|
PLM16-04195
| Groundwork | 11/16/2016 | 11/17/2016 | 11/17/2016 2:33:18 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
PLM16-03654
| Water and/or Sewer | 11/16/2016 | 11/17/2016 | 11/17/2016 1:58:07 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
PLM16-03654
| Plumbing Rough-in | 11/17/2016 | 11/17/2016 | 11/17/2016 1:57:41 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. North end of the building. 75% (north) ok and second floor drains under floor ok.
|
PLM16-03654
| Plumbing Rough-in | 11/17/2016 | 11/17/2016 | 11/17/2016 1:55:58 PM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. North end. 75% of the building and second floor piping in the ceiling ok.
|
PLM16-01527
| PLM-Aging Inspection | 11/17/2016 | 11/17/2016 | 11/17/2016 12:20:30 PM | | PASS |
|
|
|
PLM16-01527
| Sprinkler (Final) | 11/17/2016 | 11/17/2016 | 11/17/2016 12:20:14 PM | P | PASS |
|
|
DC certified
|
PLM16-01681
| Sprinkler (Final) | 11/17/2016 | 11/17/2016 | 11/17/2016 12:12:39 PM | P | PASS |
|
|
RP certified
|
PLM16-02949
| Final | 11/16/2016 | 11/17/2016 | 11/17/2016 11:42:15 AM | A | PASS |
|
|
Other contractors should be on site. If not please give me a call. Thanks. Phone #: ###-#### Inspection requested via web by Josh Johnson
|
PLM15-04235
| DOC - Permit Expired | 11/17/2016 | 11/17/2016 | 11/17/2016 11:15:59 AM | P | PASS |
|
|
Spolke with Jim. Not finishing job. Rough-in only.
|
PLM16-00054
| Plumbing Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 11:03:58 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Soubanh Senethavialy
|
PLM16-04192
| Plumbing Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 10:38:15 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Aarin Van Curen. waste test failed. Water test ok. Good to pull water test.
|
PLM16-04054
| Final | 11/16/2016 | 11/17/2016 | 11/17/2016 10:04:57 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette
|
PLM16-03807
| Water and/or Sewer | 11/17/2016 | 11/17/2016 | 11/17/2016 9:44:15 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Charles Parks
|
PLM16-04009
| Plumbing Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 9:30:33 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. Need to add an air hammer arrestor in the 2" line for the flushometer valves. Check on trim. ok to cover
|
PLM16-03834
| Final | 11/16/2016 | 11/17/2016 | 11/17/2016 9:26:45 AM | A | PASS |
|
|
Please call Justin prior to arrival he will meet you on site if needed. ###-####. Phone #: ###-#### Inspection requested via web by Maira Guzman. 2" copper water line to tenant space
|
PLM16-03872
| Final | 11/17/2016 | 11/17/2016 | 11/17/2016 8:33:56 AM | P | PASS |
|
|
dan Phone #: ###-####
|